Wednesday, 25 December 2024

Supreme Court: S. 14 Limitation Act is Applicable To Proceedings Under Arbitration & Conciliation Act

 Having considered the matter in detail, we are of the

opinion that the issue is covered by the decision of this

court in Consolidated Engg. Enterprises v. Principal

Secretary, Irrigation Dept. 2008 (7) SCC 169. (supra). {Para 9}

10. We may hasten to add that when the substantive remedies

under Sections 34 and/or 37 of the Arbitration Act are by

their very nature limited in their scope due to statutory

prescription, Arbitration and Conciliation Act, 1996.

, it is necessary to interpret the limitation

provisions liberally, or else, even that limited window to

challenge an arbitral award will be lost. The remedies under

Sections 34 and 37 are precious. Courts of law will keep in

mind the need to secure and protect such a remedy while

calculating the period of limitation for invoking these

jurisdictions.

11. Applying Section 14 of the Limitation Act, we hold that

there is sufficient cause for excluding the period commencing

from 20.10.2011 to 23.02.2012. In view of the fact that this

period is excluded, the appellant will be entitled to the

statutory remedy under Section 34 of the Act.

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS.12849-12856/2024

KIRPAL SINGH  Vs GOVERNMENT OF INDIA, NEW DELHI & ORS. 

Dated: November 21,2024. 

Citation: 2024 INSC 944.

1. Leave granted.

2. These appeals arise from the judgment and order passed by

the High Court of Punjab & Haryana at Chandigarh dated

19.10.2019 in FAO Nos. 800/2013, 7453, 7454, 8136/2014, 1278,

1290, 2000 and 2887/2015. The short question that arises for

consideration is whether the period commencing from 20.10.2011

to 20.01.2012 should be condoned under Section 14 of the

Limitation Act while reckoning the period of limitation for

filing objections under Arbitration and Conciliation Act,

19961

 incorporated in the National Highways Act, 19562

.

3. The facts relevant for our decision are that the land

belonging to the appellant was acquired under the NH Act

1 Hereinafter referred to as “the Arbitration Act”

2 Hereinafter referred to as “the NH Act”

2

leading to passing of an award dated 25.07.2011. Application

for a certified copy of the award was made on 12.08.2011 and

the same was received on 08.09.2011. Thereafter, a Regular

First Appeal was filed before the High Court on 20.10.2011 on

an erroneous understanding.

4. The Registry of the High Court notified certain defects

on 09.11.2011 and it is said to have been received by the

concerned Advocate only on 20.01.2012. It is only thereafter

when the appellant came to know about the appropriate action

available to him, being the statutory remedy under Section 34

of the Arbitration Act, and he took steps and instituted

proceedings under Section 34 of the said Act on 23.02.2012.

5. The District Judge took up the application under Section

34 of the Act and by his order dated 16.05.2012 dismissed the

same on the ground that it is barred by limitation as

determined by this Court in the case of Union of India Vs.

Popular Construction Co.3

. The appeal under Section 37 of the

Arbitration Act was also dismissed by the order impugned

before us.

6. Mr. Gaurav Agarwal, learned Senior Advocate appearing for

the appellant has submitted that his client is entitled to the

exclusion of period from 20.10.2011 to 20.01.2012 under

Section 14 of the Limitation Act. For this purpose, he relied

3 2002( 1) RCR (Civil) 124

3

on the judgment of this Court in Consolidated Engineering

Enterprises vs. Principal Secretary, Irrigation Department and

Others4

. The relevant portion of the judgment is quoted

hereunder:

“23.At this stage it would be relevant to

ascertain whether there is any express provision in

the Act of 1996, which excludes the applicability

of Section 14 of the Limitation Act. On review of

the provisions of the Act of 1996 this Court finds

that there is no provision in the said Act which

excludes the applicability of the provisions of

Section 14 of the said Act…..

Hence, Section 43 incorporating the Limitation

Act will apply to the proceedings in the

arbitration as it applies to the proceedings of a

suit in the court. Sub-section (4) of Section 43,

inter alia, provides that where the court orders

that an arbitral award be set aside, the period

between the commencement of the arbitration and the

date of the order of the court shall be excluded in

computing the time prescribed by the Limitation

Act, 1963, for the commencement of the proceedings

with respect to the dispute soc submitted. If the

period between the commencement of the arbitration

proceedings till the award is set aside by the

court, has to be excluded in computing the period

of limitation provided for any proceedings with

respect o the dispute, there is no good reason as

to why it should not be held that the to provisions

of Section 14 of the Limitation Act would be

applicable to an application submitted under

Section 34 of the Act of 1996, more particularly d

where no provision is to be found in the Act of

1996, which excludes the applicability of Section

14 of the Limitation Act, to an application made

under Section 34 of the Act. It is to be noticed

that the powers under Section 34 of the Act can be

exercised by the court only if the aggrieved party

makes an application. The jurisdiction under

Section 34 of the Act, cannot be exercised suo

motu. The total period of four months within which

an application, for setting aside an arbitral

award, has to be made is not unusually long.

Section 34 of the Act of 1996 would be unduly

4 2008 (7) SCC 169

4

oppressive, if it is held that the provisions of

Section 14 of the Limitation Act are not applicable

to it, because cases are no doubt conceivable where

an aggrieved party, despite exercise of due

diligence and good faith, is unable to make an

application within a period of four months. From

the scheme and language of Section 34 of the Act of

1996, the intention of the legislature to exclude

the applicability of Section 14 of the Limitation

Act is not manifest. It is well to remember that

Section 14 of the Limitation Act does not provide

for a fresh period of limitation but only provides

for the exclusion of a certain period. Having

regard to the legislative intent, it will have to

be held that the provisions of Section 14 of the

Limitation Act, 1963 would be applicable to g an

application submitted under Section 34 of the Act

of 1996 for setting aside an arbitral award.”

7. On the other hand, Mr. Rajat Sangwan, learned counsel

appearing for respondent Nos.1 and 2 (National Highway

Authority of India) has vehemently contended that the periods

of limitation under the Arbitration Act are sacrosanct and

these provisions are strictly interpreted by the Courts. He

would further submit that, even assuming that Section 14 of

the Limitation Act is applicable, the benefit of the said

section cannot be extended beyond 20.10.2011. In other words,

his submission is that the period commencing from 09.11.2011

to the filing of Section 34 petition being 23.02.2012, should

not be condoned.

8. Further, Mr. Rajat Sangwan, would also submit that the

language of Section 14 is mandatory and on the basis of the

said provision it cannot be said that the appellant has

exercised due diligence in approaching the Court by filing the

Section 34 petition. He also argued that strict enforcement of

time-lines under the Arbitration Act are recognized and

incorporated under the National Highways Act. For this

purpose, he referred to sub-section 7 of Section 3(G) of the

NH Act.

9. Having considered the matter in detail, we are of the

opinion that the issue is covered by the decision of this

court in Consolidated Engg. Enterprises v. Principal

Secretary, Irrigation Dept. 2008 (7) SCC 169. (supra).

10. We may hasten to add that when the substantive remedies

under Sections 34 and/or 37 of the Arbitration Act are by

their very nature limited in their scope due to statutory

prescription, Arbitration and Conciliation Act, 1996.

, it is necessary to interpret the limitation

provisions liberally, or else, even that limited window to

challenge an arbitral award will be lost. The remedies under

Sections 34 and 37 are precious. Courts of law will keep in

mind the need to secure and protect such a remedy while

calculating the period of limitation for invoking these

jurisdictions.

11. Applying Section 14 of the Limitation Act, we hold that

there is sufficient cause for excluding the period commencing

from 20.10.2011 to 23.02.2012. In view of the fact that this

period is excluded, the appellant will be entitled to the

statutory remedy under Section 34 of the Act.

12. In view of the above, we allow the appeals, set aside the

judgment and order passed by the High Court in FAO Nos.

800/2013(O&M), 2000/2015(O&M), 1278/2015(O&M), 1290/2015(O&M),

7453/2014(O&M), 7454/2014(O&M), 2887/2015(O&M) and 8136/2014

(O&M) dated 19.10.2019 and also the order of the District

Judge, Jalandhar dated 16.05.2012 and restore the Section 34

petition in Arbitration No.3435/2012 to its original number.

We further direct the District Judge, Jalandhar to issue

notice to all the parties, hear them and decide the petition

as per law.

13. With the above observations, the civil appeals are

disposed of.

14. There shall be no order as to costs.

…………………………………………J.

 [PAMIDIGHANTAM SRI NARASIMHA]


…………………………………………J.

[MANOJ MISRA]

New Delhi

November 21,2024. 

Print Page

No comments:

Post a Comment