Pages

Tuesday, 19 November 2024

Bombay High court imposes costs of five lakhs on defendant who made application for sending summary suit to Commercial courts to delay the proceeding

  Keeping in mind the objectives of the summary procedure under Order XXXVII of the CPC, so that cases falling in the specific classes of suits as specified in Rule 2 of Order XXXVII of the CPC, are disposed of expeditiously by following a summary procedure, I am of the view that the whole endeavour by the Defendants is to delay the progress of the Summary Suit. The very fact that this Application is filed after the Interim Application seeking dismissal of the Suit on the purported ground of breach of Section 12A of the said Act, itself is a pointer to the conduct of the Defendants in proceeding in the suit. Therefore, I also propose to impose exemplary costs of Rs. 5 lacs to be paid by the Defendants to the High Court Non Gazetted Ministerial Staff Association, Mumbai within a period of two weeks. {Para 30}

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION

INTERIM APPLICATION (L) NO. 6341 OF 2024

IN

SUMMARY SUIT NO. 18 OF 2023

VARANIUM CLOUD LIMITED …APPLICANT

IN THE MATTER BETWEEN

ROLTA PRIVATE LIMITED AND ANR. …PLAINTIFFS

VS

VARANIUM CLOUD LIMITED AND ANR. …DEFENDANTS

CORAM :ABHAY AHUJA, J.

PRONOUNCED ON: 11 TH NOVEMBER, 2024.

Read full Judgment here : Click here.

No comments:

Post a Comment