5.2 In the communication granting extension of time with levy
of penalty, penalty is levied by the State Government
invoking Clause 3.5.5(v) of the OPWD Code. However, it is
required to be noted that Clause 3.5.5(v) of the OPWD
Code shall be applicable in a case where the contract is
terminated. It permits the appropriate authority/State to
terminate the contract with penalty when the progress of
work is not as per the conditions of contract. Here, it is not
a case of termination of the contract. Therefore, Clause
3.5.5(v) of the OPWD Code which has been invoked in the
communication granting extension of time but with levy of
penalty shall not be applicable at all.
5.3 So far as the reliance placed upon Clause 3.5.30 of the
OPWD Code by learned counsel appearing on behalf of the
State is concerned, even under the said clause, there is no
provision for imposition of penalty while granting extension
of time. Clause 3.5.30 only provides that while
communicating to the contractor of extension of time, he
must be informed that extension is granted without
prejudice to State Government’s right to levy compensation
under relevant clause of the contract. If the relevant clause
of the contract is seen and/or considered, there is no
condition stipulated in the contract that while granting the
extension of time, there may be levy of penalty. The
relevant clause with respect to the extension of time is
Clause-4, which has been reproduced hereinabove. Neither
the contract nor the OPWD code provides for imposition of
penalty while extending the contract. Therefore, levy of
penalty while granting extension of time is wholly without
authority of the law and is illegal. The same has been
rightly set aside by the High Court.
5.4 Even otherwise, it is required to be noted that before the
levy of penalty of a particular percentage, while granting
extension of time, no opportunity of being heard has been
given to the contractor as to why the penalty may not be
imposed while granting extension of time and at what rate.
In a given case, the State Government might be justified in
imposing the penalty while granting the extension.
However, the contractor must be put to notice that
extension of time can be granted on imposition of
reasonable penalty. However, without putting the
contractor to notice, unilaterally, the State is not justified
in levying the penalty while granting extension of time.
6. In view of the above and for the reasons stated above, the
High Court has rightly set aside the penalty levied while
granting extension of time.
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4934 OF 2022
The State of Odisha & Ors. Vs Radheshyam Agrawal
Author: M.R. SHAH, J.
Dated: MARCH 24, 2023.
1. Feeling aggrieved and dissatisfied with the impugned
judgment(s) and order(s) passed by the High Court of
Orissa at Cuttack in Writ Petition Nos. 14922/2019,
10344/2021 and 20066/2019, by which, the Division
Bench of the High Court has allowed the said writ petitions
preferred by the respective contractors – original writ
petitioners and has set aside the penalty imposed while
granting the extension of time to complete the work
awarded, the State of Orissa has preferred the present
appeals.
2. For the sake of convenience, the facts in Civil Appeal No.
4934/2022 arising out of the impugned judgment and
order passed by the High Court in Writ Petition No.
14922/2019 are narrated, which in a nutshell are as
under: -
2.1 That the respondent herein – original writ petitioner, who
is a special class contractor was awarded the contract for
work of “improvement to Khariar Boden Sinapali Road
(MDR-121) from 8/000 Km. & 9/000 Km., 12/200 Km. to
20/959 Km., 23/550 Km. to 29/000 Km. & 44/300 Km. to
48/800 Km. in the District of Nuapara under NABARD
Assistance RIDF-XIII).” As per the contract and work order,
the work was to be completed by 12.09.2009. However, the
contractor could not complete the work within the
stipulated period and continued up to 12.03.2014. He
completed the work by 12.03.2014. The contractor –
original writ petitioner applied for extension of time for the
work. The request for extension of time came to be
accepted and allowed by the appropriate authority/State
Government vide order dated 07.02.2019, without price
escalation during the extended period from 13.09.2009 to
12.03.2014 but with levy of penalty @ 0.25% over the
value of the work done during the extended period as per
para 3.5.5(v) of Odisha Public Work Dept. Code (OPWD
Code) Volume-I.
2.2 Levy of penalty @ 0.25% while granting extension of time
from 13.09.2009 to 12.03.2014 was the subject matter of
writ petition before the High Court.
2.3 It was the case on behalf of the original writ petitioner –
contractor before the High Court that the levy of penalty
while granting extension of time was wholly impermissible.
It was submitted that para 3.5.5(v) of OPWD Code Volume-
I under which the penalty was levied could not have been
invoked as the penalty under the said para can be imposed
only in a case where the contract is terminated.
2.4 On the other hand, it was the case on behalf of the State
that as there was a delay on the part of the contractor in
not completing the work within the stipulated period and
the contractor applied for extension of time which came to
be accepted by the State Government, it was open for the
department/State to levy the penalty for the delayed
period.
2.5 Accepting the submission made on behalf of the original
writ petitioner – contractor that the levy of penalty while
granting the extension of time was illegal and arbitrary and
beyond para 3.5.5(v) of OPWD, by the impugned judgment
and order, the High Court has set aside the levy of penalty
which is the subject matter of present appeal.
2.6 In Civil Appeal Nos. 4935 and 4936/2022, similar
penalties have been levied by the State, however, the
percentage of the penalty varies. On a similar reasoning,
the High Court has set aside the levy of penalties in the
said cases also. Hence, the present appeals by the State of
Orissa.
3. Shri Sibo Sankar Mishra, learned counsel appearing on
behalf of the State has vehemently submitted that it is not
in dispute and it cannot be disputed that the contractor
did not complete the work within the stipulated time and
as such, there was a delay on the part of the contractor in
completing the work and that the contractor applied for
extension of time which came to be allowed by the State
Government, however, subject to payment of penalty on
the value of the work done during the extended period.
3.1 It is further submitted that as such on conjoint reading of
Clause 2(a) & (b), Clause 4 of the terms and conditions of
the contract and Clause 3.5.30 of OPWD Code, the State
Government has the power to impose penalty for delay in
work under the contract.
3.2 It is contended that the High Court has failed to appreciate
that there was a huge delay in completion of the work
under the contract and therefore, merely because of
mentioning of the penalty being imposed under a different
provision, the contractor shall not be entitled to claim any
equitable right of removal the imposition of penalty.
3.3 Making the above submissions and relying upon the
relevant clause of the contract and relevant clauses of
OPWD Code, it is prayed that the present appeals be
allowed.
4. All these appeals are vehemently opposed by Shri
Shubhranshu Padhi, learned counsel appearing on behalf
of the respective respondents – original writ petitioners.
4.1 It is vehemently submitted by Shri Padhi, learned counsel
appearing on behalf of the respective respondents –
original writ petitioners that in the facts and
circumstances of the case, the High Court has not
committed any error in setting aside the penalty levied
while granting extension of time.
4.2 It is further submitted that in the communication/order
granting extension of time but with penalty, the State
Government has relied upon Clause 3.5.5(v) of OPWD
Code. That as rightly observed by the High Court, the said
clause shall not be applicable while imposing penalty while
granting extension of time. It is contended that Clause
3.5.5(v) shall be applicable in a case where the contract is
terminated due to the failure on the part of the contractor
to carry out the work. That in the present case, it was not
a case of termination of the contract, but of extension of
time. That therefore, the High Court has rightly observed
that the levy of penalty while granting extension of time
was bad in law.
4.3 It is further contended that during the course of the
submissions learned counsel appearing on behalf of the
State has relied upon Clause 3.5.30 of the OPWD Code.
That however, even the said Clause 3.5.30 of the OPWD
Code does not permit the State to levy penalty while
granting extension of time.
4.4 It is averred that even otherwise, once the time is extended
on the application submitted by the contractor that there
was a genuine reason for which the contractor could not
complete the work within the stipulated time, thereafter, it
was not open for the State to levy/impose the penalty
while extending the time that too, without giving any
opportunity of being heard to the contractor on the
quantum of penalty.
4.5 Making the above submissions, it is prayed that the
present appeals be dismissed.
5. Having heard learned counsel appearing on behalf of the
respective parties and having gone through the impugned
judgment(s) and order(s) passed by the High Court, the
short question which is posed for consideration of this
Court is whether the State Government is justified in
levying the penalty while granting extension of time in
favour of the contractor when the contractor fails to
complete the work within stipulated time under the
contract and subsequently, completes the work beyond the
period prescribed under the contract?
5.1 In order to consider the aforesaid issue, the relevant
clauses of the contract and OPWD Code, are required to be
referred to and considered, which are as under: -
Relevant provision of the contract agreement
Extension of Time
Clause-4 "If the contractor shall desire an extension of
the times for completion of the work, on the ground of his
having been unavoidably hinder in its execution or any
other ground he shall apply in writing to the Executive
Engineer within 30 days of the date of the hindrance on
account of which he desires such extension as aforesaid
and the Executive Engineer shall, if in his opinion (which
shall be final) reasonable grounds be shown thereof,
authorize such extension of time, if any, as may in his
opinion, be necessary or proper. The Executive Engineer
shall at the time inform the contractor whether he claims
compensation for delay.”
Relevant provisions of the OPWD Code
Clause (V) of para 3.5.5 of the OPWD Code, Vol. I: -
"Percentage Contract will be in addition of item rate, lump
sum contractors etc. In such contracts the schedule of
quantities shall mention estimated rate of such item and
amount thereof. The Contractor has to mention
percentage excess or less over the estimated cost (in
figures as well as words) in the prescribed format
appended to the tender document. The Contractors
participated in the tender for more than one work may
offer conditional rebate. Rebate offer submitted in
separate sealed envelope shall be opened, declared and
recorded first. The rebate so offered, shall be considered
after opening of all Page 3 of 5 packages called in the
same tender notice. The Contractors who wish to tender
for two or more work shall submit separate tender for
each. Each tender shall have the name and number of the
works to which they refer, written on the envelope. The
adopted format for percentage rate is same as that of the
form adopted for item rate tenders but the word "item
rate" shall be replaced by "percentage rate" and the
contract form may be named as P-1. In this for time is the
essence. The Contractor is required to maintain a certain
rate of progress specified in the contract. The contract
can also be terminated with penalty when the progress of
work is not as per the conditions of contract. The quantity
mentioned can be increased or reduced to the extent of
10% for individual items subject to a maximum of 5%
over the estimated cost. If it exceeds the limit stated
above prior approval of competent authority is mandatory
before making any payment. The period of completion is
fixed and cannot be altered except in case of exceptional
circumstances with due approval of next higher authority.
….”
Clause 3.5.30 of the OPWD Code
“Application for extension of time for the completion of a
work on the grounds of unavoidable hindrance or any
other grounds shall be submitted by the contractor within
30 days of such hindrance and the Divisional Officer shall
authorise or recommend such extension of time as
deemed necessary or proper within fifteen days of the
receipt of such an application. In cases where the
sanction of the higher authority to the grant of extension
of time is necessary, the Divisional Officer should send
his recommendation as expeditiously as possible. The
higher authority should communicate his decision within
60 days from the date of receipt on recommendation in
his office. If the orders of the competent authority are not
received in time the Divisional Officer may grant
extension of time under intimation to the concerned
authorities so that the contract might remain in force, but
while communicating this extension of time, he must
inform the contractor that extension is granted without
prejudice to Govt.'s right to levy Compensation under
relevant clause of the contract.”
5.2 In the communication granting extension of time with levy
of penalty, penalty is levied by the State Government
invoking Clause 3.5.5(v) of the OPWD Code. However, it is
required to be noted that Clause 3.5.5(v) of the OPWD
Code shall be applicable in a case where the contract is
terminated. It permits the appropriate authority/State to
terminate the contract with penalty when the progress of
work is not as per the conditions of contract. Here, it is not
a case of termination of the contract. Therefore, Clause
3.5.5(v) of the OPWD Code which has been invoked in the
communication granting extension of time but with levy of
penalty shall not be applicable at all.
5.3 So far as the reliance placed upon Clause 3.5.30 of the
OPWD Code by learned counsel appearing on behalf of the
State is concerned, even under the said clause, there is no
provision for imposition of penalty while granting extension
of time. Clause 3.5.30 only provides that while
communicating to the contractor of extension of time, he
must be informed that extension is granted without
prejudice to State Government’s right to levy compensation
under relevant clause of the contract. If the relevant clause
of the contract is seen and/or considered, there is no
condition stipulated in the contract that while granting the
extension of time, there may be levy of penalty. The
relevant clause with respect to the extension of time is
Clause-4, which has been reproduced hereinabove. Neither
the contract nor the OPWD code provides for imposition of
penalty while extending the contract. Therefore, levy of
penalty while granting extension of time is wholly without
authority of the law and is illegal. The same has been
rightly set aside by the High Court.
5.4 Even otherwise, it is required to be noted that before the
levy of penalty of a particular percentage, while granting
extension of time, no opportunity of being heard has been
given to the contractor as to why the penalty may not be
imposed while granting extension of time and at what rate.
In a given case, the State Government might be justified in
imposing the penalty while granting the extension.
However, the contractor must be put to notice that
extension of time can be granted on imposition of
reasonable penalty. However, without putting the
contractor to notice, unilaterally, the State is not justified
in levying the penalty while granting extension of time.
6. In view of the above and for the reasons stated above, the
High Court has rightly set aside the penalty levied while
granting extension of time. Under the circumstances, the
present appeals fail and the same deserve to be dismissed
and are accordingly dismissed. In the facts of the cases,
there shall be no order as to costs.
………………………………….J.
[M.R. SHAH]
NEW DELHI; ………………………………….J.
MARCH 24, 2023 [B.V. NAGARATHNA]
No comments:
Post a Comment