In view of the aforesaid, a compromise pursis at
Exh.13 duly signed by the parties to the appeal, was
presented before the first appellate Court on 3/9/2020 with
the following prayer therein :
“The appeal be ordered as withdrawn in terms of
the Compromise and the Decree of R.C.S.
No.119/2015 passed by C.J.S.D. (M.C.A.),
Aurangabad on 9.9.2019 be confirmed as per terms
and conditions of this Compromise and oblige.” {Para 25}
26. Thereafter the Law Officer of the AMC submitted a
pursis dated 15/9/2020, whereunder the AMC reneged on the
compromise pursis. The first appellate Court, therefore, did
not endorse the compromise. The appeal was heard on its
merits and came to be dismissed.
35. The subsequent event of the compromise between
the AMC and the plaintiff firm or concessionaire is a fact not in
dispute. Most of the terms of compromise were executed in
nature. True, some of them were executory. To be specific,
additional FSI was to be granted permitting further
construction. It is also true that, the subject matter of the
present appeal is not the enforcement of the terms of the
compromise.
This Court, relying on decision of the Apex Court
in case of Nidhi (supra), finds that, when the AMC went back
on its promise and it has offered every excuse therefor, this
Court finds that, those facts need not be brought on record by
amending the respective pleadings. This subsequent event is
the admitted fact. The defendant AMC is a local authority. It
has a battery of lawyers on its panel to advice it. True, it has
every authority not to take the compromise terms to logical
conclusion. The Court seized of the present Second Appeal,
however, could not be oblivious to the factum of settlement.
In the present case, a compromise pursis was
submitted for withdrawal of the appeal. Be that as it may.
This Court is neither endorsing the compromise nor enforcing
the same. The factum of compromise, however, is viewed to
hold the defendant – AMC to have diluted its stand on the
decision of cancelling the lease agreement for illegality
committed by the plaintiff firm and/or its sister concern.
In view of the above, the substantial questions of
law are answered accordingly.
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
SECOND APPEAL NO.335 OF 2022 WITH
CIVIL APPLICATION NO.8534 OF 2022
M/s Shalaka Engineers and JV Vs Aurangabad Municipal Corporation,
CORAM : R. G. AVACHAT, J .
Dated : 22nd December, 2022
This is original plaintiff’s appeal from appellate
decree (Second Appeal). The plaintiff is a partnership firm. It
filed a suit, being Regular Civil Suit No.119/2015 against
Aurangabad Municipal Corporation (AMC) for the following
reliefs :-
(a) By Decree of Declaration it be declared that
the order dated 24/7/2015 passed by the
Defendant terminating the Agreement of
Lease dated 16/10/2009 is illegal, null and
void and be quashed.
(b) By Decree of Mandatory Injunction the
Defendant be directed to remove the seal
affixed from the suit property as described in
the claim clause and description clause of the
plaint on 25/7/2015, vide Panchanama of the
even date.
(c) By decree of Perpetual Injunction the
Defendant be restrained from creating any sort
of third party interest in the suit property of
any nature and also from causing obstruction
and interference in the peaceful possession of
the Plaintiff of the suit property as described
in the claim clause and description clause of
the plaint.
2. The trial Court decreed the suit vide its judgment
dated 9/9/2019. The AMC, therefore, preferred first appeal,
being Regular Civil Appeal No.254/2019. The appellate Court,
vide its judgment and decree dated 14/1/2022, reversed the
decree passed by the trial Court and dismissed the suit.
3. The facts giving rise to this Second Appeal are as
follows :-
An open site bearing C.T.S. No.16262, situated at
Jyotinagar, Aurangabad belongs to AMC. A swimming pool
complex with amenities was proposed to be constructed
thereon under Build Operate and Transfer (BOT) Scheme. A
concessionaire agreement was, therefore, executed between
AMC and Shalaka Engineers & Joint Ventures (JV) on
7/5/2007. Shalaka Engineers and Joint Ventures, under the
concessionaire agreement, was authorised to lease out
swimming pool complex to anyone on certain terms and
conditions. A tri-party agreement was executed between
AMC on one hand and Shalaka Engineers and JV and plaintiff
firm on the other. Needless to mention, the plaintiff firm is a
sister concern or the subsidiary of Shalaka Engineers and JV.
The plaintiff firm was given the swimming pool complex on
lease.
4. All was well for initial period of six years. The
project was run smoothly. As per the case of the AMC, the
plaintiff firm committed breach of the terms and conditions of
agreement. The plaintiff firm made unauthorised and illegal
construction on the open land. A Hukka Parlour was operated
from one of the shop blocks in swimming pool complex. A
massage parlour was opened in another block. Females were
engaged as masseuse. Under the guise of massage parlour,
illegal activities were performed. A restaurant was opened at
the swimming pool. One side transparent glass partition was
raised between the restaurant and the swimming pool. It was
only with a view that the customers at the restaurant could
watch swimming activities of women. The AMC received
number of complaints from the residents. The AMC
authorities, therefore, paid visit to the swimming pool. The
police too paid similar visit. Crimes came to be registered.
The concerned pleaded guilty for the offence of running Hukka
Parlour. They were sentenced to pay a fine. The AMC first
issued the plaintiff firm a notice, calling upon it to give
explanation. The notice was purportedly issued in terms of
clause No.5.6 of the lease agreement. The AMC authorities,
after having realised that activities committed by the plaintiff
firm were illegal, invoked clause 5.19. Lease agreement came
to be cancelled. The swimming pool complex came to be
placed under seal.
5. The plaintiff firm initially filed Writ Petition against
the AMC. The petition came to be disposed of with a direction
to AMC to de-seal the premises and take appropriate action in
accordance with law. The plaintiff, meanwhile, preferred
Municipal Appeal, under Section 81(F) of the Bombay
Provincial Municipal Corporations Act (for short, the Act). The
appeal came to be dismissed with the observations that the
plaintiff has not challenged the order of termination of the
lease. The plaintiff firm, therefore, filed the suit.
6. The trial Court decreed the suit, observing the
plaintiff to have not been given due opportunity of hearing
before the action impugned in the suit was taken by the AMC.
The first appellate Court upset the decree passed by the trial
Court. It observed that, the plaintiff firm indulged in illegal
activities and thus committed breach of the terms of the lease
agreement. The AMC was, therefore, justified in invoking
clause 7.19 of the lease agreement to terminate the same.
7. This Second Appeal is being finally decided at
admission stage on the following substantial questions of law,
although the learned counsel for the appellant submitted no
such questions of law arise herein.
(I) Whether in the facts and circumstances of the case
the first appellate Court was justified in reversing
the decree passed by the trial Court ?
(II) Whether in view of the subsequent events,
particularly settlement between the parties,
interference with the impugned decree is
warranted ?
8. Point No.I :-
Clause (1) of the Concession Agreement dated
7/5/2007 executed between AMC and M/s Shalaka Engineers
and JV reads :-
“ (1) Scope of work :- The project scheme is to
develop the part of open space by constructing
swimming pool with Amenities through
entrepreneur/ bidder. The project scheme
involves construction of swimming pool, children
swimming pool with all amenities like- health
club and health care facilities shower area, sports
shop etc. as per D.C. rules. The successful
entrepreneur/ bidder will be responsible for the
construction of the swimming pool complex by
his own funds. The Aurangabad Municipal
Corporation owner of land of project will allow
the successful entrepreneur/ bidder to recover his
investment by giving the successful entrepreneur/
bidder the right to lease out swimming pool
complex having land area 2114.75 sq.mt. with
constructed area 422.95 sq.mt. on a long term
lease of 30 years further renewal for maximum
99 years to occupants of his choice on payment
of non refundable deposit or by making members
of his choice by charging membership fees to
avail the swimming pool complex facilities to
recover his investment on the said project. The
occupant of swimming pool complex will have to
pay rent Rs.5/- per sq.mt. per month on
chargeable area to A.M.C. for first 30 years.
A.M.C. will renew this lease for further 30 years
on same rent a max. of 99 years.”
9. Admittedly, the plaintiff firm, a subsidiary of M/s
Shalaka Engineers and J.V., filed the suit in a capacity as an
occupant of the swimming pool complex. A tripartite
agreement in the nature of B.O.T. agreement for lease was
executed on 16/10/2009 between AMC on one hand and the
plaintiff firm with M/s Shalaka Engineers and J.V. on the other.
In the definition clause of the said agreement, the term
“Concessionaire’s Event of Default” has been defined as :-
“Concessionaire’s Event of Default” means the
concessionaire failure to perform any of its
obligations in accordance with the provisions of
this agreement and or the concession agreement.”
10. Clauses 5.6 and 7.19 of the B.O.T. agreement for
lease (Exhibit B) are very much relevant to decide the present
Second Appeal. Both the clauses are, therefore, reproduced
for ready reference :-
“5.6: In the occupant event of default after the
concession period, AMC shall serve upon the
occupant a notice in writing mentioning therein
the default and shall time, as may deem fit and
proper considering the nature of default, to the
occupant for removal/ rectification of the default.
In case the occupant does not remove/ rectify the
default, AMC is empowered to terminate this
lease agreement by giving a one month notice in
this regard.”
7.19: That the occupant shall not carry on any
illegal activity in the leased premises. In case he/
she/ it does so, the the lease granted under this
agreement shall liable to be terminated forthwith
without notice.”
11. It is the case of the AMC that, the concessionaire,
M/s Shalaka Engineers and J.V. committed illegal activities on
the leased premises and, therefore, the agreement of lease
came to be terminated invoking clause 7.19. The illegal
activities stated to have been committed are :-
Unauthorised construction in the parking space,
open space. Hukka parlour was being run. Restaurant, music
and dancing class and massage parlour were operated
unauthorisedly. A glass partition was raised between the
swimming pool and the restaurant. The glass was of such a
type (transparent from one side), whereby swimming
activities of women could be seen from the pool side
restaurant.
12. Learned counsel for the AMC would submit that,
the concessionaire or even the plaintiff firm has admitted in
no uncertain terms the commission of illegal activities. The
AMC was, therefore, justified in invoking clause 7.19 of the
lease agreement. According to him, M/s Shalaka Engineers
and J.V. had preferred a Municipal Appeal, challenging the
AMC’s action of taking possession of the swimming pool
complex. The appeal came to be dismissed. The order
passed therein had not been challenged. As such, the said
order attained finality. Validity of clause 7.19 has not been
challenged. A team of officials of the AMC has paid visit to
the swimming pool complex. First Information Reports have
been lodged against the representatives of the plaintiff firm.
In case of illegal running of Hukka parlour, the concerned
pleaded guilty and even paid fine. Section 43 of the Indian
Penal Code defines the term ‘illegal’ to mean everything which
is an offence or which is prohibited by law, or which furnishes
ground for a civil action; and a person is said to be “legally
bound to do” whatever it is illegal in him to omit.
13. Complaints from residents of Jyotinagar locality,
whereat the swimming pool complex is situated, were
received. Because of a foot-fall at the swimming pool
complex on account of illegal activities, life of women in the
vicinity became unsafe. Attention of this Court was adverted
to the oral evidence in the case.
14. Learned counsel for the plaintiff firm would, on the
other hand, submit that, the alleged illegal activities have
already been done away with. Running of Hukka parlour is
not such an activity warranting action under clause 7.19. He
relies on the judgment of the Apex Court in case of Narinder
S. Chadha Vs. Municipal Corporation of Greater Mumbai [AIR
2015 SC 756]. The relevant provisions of the Cigarettes and
Other Tobacco Products (Prohibition of Advertisement and
Regulation of Trade and Commerce, Production, Supply and
Distribution) Act, 2003 were also relied on.
15. A team of officers of AMC paid visit to the
swimming pool complex on 3/7/2015. A panchanama of the
visit (Exh.52) was drawn. The AMC issued M/s Shalaka
Engineers and J.V. a communication dated 17/7/2015
(Exh.57) in relation to illegalities noticed at the swimming
pool complex. The last clause of the communication states in
so many words that, it was a notice in terms of clause 5.6 of
the lease agreement. The plaintiff firm gave its response
dated 23/7/2015 to the notice (Exh.57). It half-heartedly
denied commission of illegal activities at the swimming pool
complex. It was its stand that the restaurant was being run
for only refreshment purposes. It was given to an operator-
Mr. Amol Pawar. The Hukka parlour was being run without the
knowledge of the plaintiff firm. The activities such as parlour,
music and dancing class would in no way be termed to be
illegal. No complaint was ever received in that regard. The
AMC was ultimately requested to withdraw the notice.
16. It appears that, the AMC had constituted a three
member committee of its officials purportedly on the
directions of the High Court in a Writ Petition. This Court does
not find any such direction asking the AMC to constitute a
committee. Be that as it may, a Writ Petition filed by M/s
Shalaka Engineers and J.V. (Writ Petition No.6834/2015) was
disposed of vide order dated 10/7/2015 with the following
observations :-
“(1) Heard. Learned counsel appearing for
Municipal Corporation, Aurangabad, on
instructions, makes a statement that the Municipal
Corporation shall draw panchanama, tomorrow i.e.
on 11th July, 2015 and de-seal the premises, i.e.
swimming pool complex with amenities situated at
Plot No.CTS No.16261 at Jyotinagar, Aurangabad;
and the Corporation may also continue with the
action, which is already initiated.
2) It would be open for the Municipal
Corporation to take appropriate steps and action in
accordance with the BOT lease agreement for lease
and in consonance with the provisions of law.”
The aforesaid order, in no way, suggests the AMC
to have been given any direction to constitute a three
member committee.
17. The Committee gave its report to the
Commissioner, AMC on 23/7/2015. It concluded the plaintiff
firm (occupant) to have committed unauthorised activities
and, therefore, it would be desirable to cancel the lease
agreement, taking recourse to clause 7.19. The
Commissioner, AMC, therefore, vide order (Exh.79) dated
24/7/2015, cancelled the lease agreement. The swimming
pool complex came to be placed under its seal.
18. The reasoning given by the first appellate Court
that recourse to clause 5.6 could have only been taken only
during the first year of the lease agreement, was unfounded.
It was nobody’s case as well. This Court, therefore, do not
propose to advert to the said reasonings.
19. A reference to relevant oral evidence would not be
out of place at this stage itself.
The plaintiff’s witness Sunil Mulchand Raka has
admitted in no uncertain terms to have had made
unauthorised illegal construction in the open space and
parking area. He also admitted that, Hukka parlour was being
operated. Undisputedly, a particular type of glass through
which activities at the swimming pool could be seen from the
pool side restaurant was raised. It is also not in dispute that,
a massage parlour was being operated from one of the blocks
in swimming pool complex.
As against this, the witness examined on behalf of
the AMC admitted that, M/s Shalaka Engineers and J.V. has
filed the suit in the capacity of occupant. He also admitted
that, M/s Shalaka Engineers and J.V. was appointed as
occupant in dual capacity as functional and occupant. In case
of any default, objectionable wrong on the swimming pool
complex, could be rectified as per clause 5.6. He also
admitted that, there was no hearing or decision on the basis
of letter dated 17/7/2015. BOT Cell of AMC had not put up a
proposal for termination of lease agreement. The
Commissioner did not obtain approval of general body prior to
taking decision of termination of agreement of lease. The
witness went on to admit that, so called illegalities were
removed/ done away with before 25/7/2015 itself. He was
specific to state that, all illegalities were removed between
3/7/2015 and 24/7/2015.
20. Admittedly, the representatives of the plaintiff firm
pleaded guilty in a prosecution instituted under Section 33(w)
read with Section 131 of the Mumbai Police Act and under
Section 4 read with 21 of the Cigarettes and Other Tobacco
Products (Prohibition of Advertisement and Regulation of
Trade and Commerce, Production, Supply and Distribution)
Act, 2003 (for short the Act). It was relating to running of a
Hukka parlour/ restaurant without obtaining a permit or
licence to operate the same. They paid a fine of Rs.1200/-
each. It is also true that, an F.I.R. has been lodged for
illegalities, namely unauthorised construction etc.
21. Section 4-A of the Act speaks of prohibition of
Hukka Bar. The Section reads :-
“4-A. Prohibition of hookah bar.
Notwithstanding anything contained in this Act,
no person shall, either on his own or on behalf of
any other person, open or run any hookah bar in
any place including the eating house.
Explanation:- The term “eating house” shall
have the same meaning as assigned to it in clause
(5A) of section 2 of the Maharashtra Police Act.
Section 3-ee of the Act defines the term “hookah
bar” to mean an establishment where people gather to smoke
tobacco from a communal hookah or narghile which is
provided individually.
Section 21-A of the said Act came to be introduced
by way of amendment in 2018, whereunder, contravention of
provision of Section 4-A is made punishable with
imprisonment which may extend to three years and with fine
which may extend to one lakh rupees but which shall not be
less than fifty thousand rupees. This was not the legal
position when the offence of running Hukka parlour was
committed. At the relevant time, it was an offence under
Mumbai Police Act. The contravention was punishable with
imposition of fine only.
22. Although motive of the operators of pool side
restaurant and massage parlour was oblique, there is nothing
to suggest that under the guise of running a massage parlour,
illegal activities like prostitution was being run.
23. True, the fact remains that the plaintiff firm
committed illegal activities in operating the swimming pool
complex. The question is whether the AMC was justified in
cancelling the lease agreement, taking recourse to clause
7.19. True, the said clause empowers the AMC to cancel the
lease agreement at once, once any illegal activity is noticed.
Admittedly, the communication/ notice dated 17/7/2015 was
issued to M/s Shalaka Engineers and J.V. taking recourse to
clause 5.6 of the lease agreement. The same suggests the
AMC authorities had called upon the noticee to rectify the
wrong within a notice period of one month. Admittedly, all
the illegal activities were removed before 24/7/2015. When
the AMC takes recourse to clause 5.6 of the lease agreement,
the same suggests that the illegal activities committed by M/s
Shalaka Engineers and J.V. were not of such a nature
compelling to have a recourse to clause 7.19. Admittedly, the
noticee - M/s Shalaka Engineers and J.V. gave its response to
the communication dated 17/7/2015, calling upon the AMC to
withdraw the notice since unauthorised construction was
removed and other illegal activities were ceased. In this
factual backdrop, the AMC ought not to have taken recourse
to clause 7.19 to cancel the lease agreement and place the
swimming pool complex under seal.
24. Had the AMC really been serious over the
illegalities/ lapses committed by the plaintiff firm, it would not
have entered into a compromise. Pending the first appeal,
tenure of the elected body of people’s representatives came to
an end. The Municipal Commissioner became the
Administrator of the AMC. He is said to have taken a stock of
all BOT projects. He decided to enter into a compromise with
M/s Shalaka Engineers and J.V. A copy of the minutes of the
meeting dated 31/8/2020 indicates that on negotiations with
Sunil Raka, developer of the swimming pool complex, a
revised agreement of lease was decided to be entered into.
The developer agreed to enhance the lease amount from
Rs.5/- to Rs.15/- per sq.mtr. Thereafter on 28/8/2020, the
Municipal Commissioner-cum-Administrator approved the
proposal regarding entering into a renewed lease. For better
appreciation, the order approving the proposal is reproduced
below in verbatim.
{Vernaculars omitted}
25. In view of the aforesaid, a compromise pursis at
Exh.13 duly signed by the parties to the appeal, was
presented before the first appellate Court on 3/9/2020 with
the following prayer therein :
“The appeal be ordered as withdrawn in terms of
the Compromise and the Decree of R.C.S.
No.119/2015 passed by C.J.S.D. (M.C.A.),
Aurangabad on 9.9.2019 be confirmed as per terms
and conditions of this Compromise and oblige.”
26. Thereafter the Law Officer of the AMC submitted a
pursis dated 15/9/2020, whereunder the AMC reneged on the
compromise pursis. The first appellate Court, therefore, did
not endorse the compromise. The appeal was heard on its
merits and came to be dismissed.
27. The learned counsel for the AMC made very many
submissions in this regard. He first took this Court through
the legal dictionary meaning of the term ‘compromise’. He
then relied on relevant provisions of Order 23 of the Code of
Civil Procedure. He also relied on the judgments of the Apex
Court in this regard. According to him, the decree in terms of
compromise was not passed. The first appeal was argued on
its own merits without taking recourse to the subsequent
event of proposed compromise. The terms of compromise
were not in the nature of concluded contract. The plaintiff has
filed a Writ Petition before this Court for enforcement of the
terms of compromise. No ground in that regard has been
made in the memo of this Second Appeal. An affidavit of a
Law Officer was placed on record in justification of going back
on the terms of compromise. It was further submitted that,
the first appellate Court did not verify the compromise memo.
The compromise was withdrawn before it received sanctity of
the orders of the Court. Till the stage of verification of the
compromise, the compromise was not concluded and consent
to the same could be withdrawn. It was also submitted that,
since there was an interim order against the AMC, preventing
it from creating any third party interest in relation to the
swimming pool complex, it was thought fit to take appropriate
steps in accordance with law for putting the property for
beneficial use of citizens. Complaints from the residents
were, however, received. A proposal of compromise got wide
publicity in the dailies. Ex-Corporators were up in ante. It
was, therefore, thought expedient not to go ahead with the
compromise. Relevant provisions of Order 23 Rule 3 have
also been adverted to. This Court do not propose to
reproduce the same.
28. A brief reference to the authorities relied on by the
learned counsel for the AMC is necessary before arriving at a
conclusion.
In case of Shyama Sundar & ors. Vs. Ram Kumar
& anr. [ AIR 2001 SC 2472 ], the issue involved was, whether
amended Section 15 of Punjab Pre-emption Act had
retrospective effect. The Hon’ble Supreme Court held that,
the Amending Act being prospective in operation, did not
affect the rights of the parties to the litigation on the date of
adjudication of preemption suit and the appellate Court was
not required to take into account or give effect to the
substituted Section 15 introduced by the Amending Act.
This Court has carefully perused the entire
judgment and specifically paragraphs No.29 and 30 thereof.
The said judgment is quite distinguishable and would,
therefore, be of no assistance to AMC in the facts and
circumstances of the case.
29. The judgment of the Apex Court in case of Sushil
Kukar Agarwal Vs. Meenakshi Sadhu & ors. (Civil Appeal
No.1129 of 2012) speaks of a suit for specific performance of
development agreement. Provisions of Section 14 of the
Specific Relief Act, 2018 were under consideration in the said
appeal.
30. The facts in case of R. Rathinavel Chettiar Vs. V.
Sivaraman [ (1999) 4 SCC 89 ] suggest that, permission to
withdraw a suit after passing decree and matter being at
appellate stage, was not granted to the plaintiff since the
subject matter of the suit (immovable property) was sold
pending the suit. The assignees became parties on the basis
thereof. The Court found that, allowing of application for
withdrawal of the suit by plaintiff would have been prejudicial
to valuable rights that came to be vested in the transferees.
31. The judgment of Apex Court in Banwari Lal Vs.
Smt. Chando Devi (through L.R.) & anr. [ AIR 1993 SC 1139 ]
speaks of, that even after a compromise has been recorded,
the Court concerned can entertain an application under
Section 151 of the Code of Civil Procedure questioning the
legality or validity of the compromise. Rule 3-A of Order 23
bars a remedy of suit to set aside a decree on the ground that
the compromise of which the decree was based, was not
lawful.
32. This Court has also perused the Apex Court
judgment in case of State of Punjab & ors. Vs. Ganpat Raj
[ AIR 2006 SC 3089 ] and the judgment of Madras High Court
in case of Athappa Gounder Alias Poosari Gounder Vs.
Periasami Gounder [ AIR 1956 Madras 344 ] to find to have
no bearing on the fate of the present Second Appeal.
33. In case of Nidhi Vs. Ram Kripal Sharma (D)
through L.Rs. (Civil Appeal No. 1008 of 2017), the Apex Court
observed :-
15. Ordinarily, rights of the parties stand
crystallised on the date of institution of the suit.
However, the court has power to take note of the
subsequent events and mould the relief accordingly.
Power of the court to take note of subsequent events
came up for consideration in a number of decisions. In
Om Prakash Gupta vs. Ranbir B. Goyal (2002) 2 SCC
256, this Court held as under:-
“11. The ordinary rule of civil law is that the
rights of the parties stand crystallised on the
date of the institution of the suit and,
therefore, the decree in a suit should accord
with the rights of the parties as they stood at
the commencement of the lis. However, the
Court has power to take note of subsequent
events and mould the relief accordingly
subject to the following conditions being
satisfied: (i) that the relief, as claimed
originally has, by reason of subsequent
events, become inappropriate or cannot be
granted; (ii) that taking note of such
subsequent event or changed circumstances
would shorten litigation and enable complete
justice being done to the parties; and (iii) that
such subsequent event is brought to the notice
of the court promptly and in accordance with
the rules of procedural law so that the
opposite party is not taken by surprise. In
Pasupuleti Venkateswarlu v. Motor & General
Traders (1975) 1 SCC 770 this Court held that
a fact arising after the lis, coming to the
notice of the court and having a fundamental
impact on the right to relief or the manner of
moulding it and brought diligently to the
notice of the court cannot be blinked at. The
court may in such cases bend the rules of
procedure if no specific provision of law or
rule of fair play is violated for it would
promote substantial justice provided that there
is absence of other disentitling factors or just
circumstances. The Court speaking through
Krishna Iyer, J. affirmed the proposition that
the court can, so long as the litigation pends,
take note of updated facts to promote
substantial justice. However, the Court
cautioned: (i) the event should be one as
would stultify or render inept the decretal
remedy, (ii) rules of procedure may be bent if
no specific provision or fair play is violated
and there is no other special circumstance
repelling resort to that course in law or
justice, (iii) such cognizance of subsequent
events and developments should be cautious,
and (iv) the rules of fairness to both sides
should be scrupulously obeyed.”
Om Prakash Gupta’s case was referred with
approval in Ram Kumar Barnwal vs. Ram
Lakhan (Dead) (2007) 5 SCC 660.
34. While in case of Bachhaj Nahar Vs. Nilima Mandal
& anr. (Civil Appeal Nos.5798-5799 of 2008), the Apex Court
has observed :-
“8. . . . . . . . . . . . . .
(i) No amount of evidence can be looked into,
upon a plea which was never put forward in the
pleadings. A question which did arise from the
pleadings and which was not the subject matter of
an issue, cannot be decided by the court.
(ii) A Court cannot make out a case not pleaded.
The court should confine its decision to the
question raised in pleadings. Nor can it grant a
relief which is not claimed and which does not
flow from the facts and the cause of action alleged
in the plaint.
(iii) A factual issue cannot be raised or considered
for the first time in a second appeal.
Civil Procedure Code is an elaborate codification
of the principles of natural justice to be applied to
civil litigation. The provisions are so elaborate that
many a time, fulfillment of the procedural
requirements of the Code may itself contribute to
delay. But any anxiety to cut the delay or further
litigation, should not be a ground to float the
settled fundamental rules of civil procedure. Be
that as it may. We will briefly set out the reasons
for the aforesaid conclusions.”
35. The subsequent event of the compromise between
the AMC and the plaintiff firm or concessionaire is a fact not in
dispute. Most of the terms of compromise were executed in
nature. True, some of them were executory. To be specific,
additional FSI was to be granted permitting further
construction. It is also true that, the subject matter of the
present appeal is not the enforcement of the terms of the
compromise.
This Court, relying on decision of the Apex Court
in case of Nidhi (supra), finds that, when the AMC went back
on its promise and it has offered every excuse therefor, this
Court finds that, those facts need not be brought on record by
amending the respective pleadings. This subsequent event is
the admitted fact. The defendant AMC is a local authority. It
has a battery of lawyers on its panel to advice it. True, it has
every authority not to take the compromise terms to logical
conclusion. The Court seized of the present Second Appeal,
however, could not be oblivious to the factum of settlement.
It is not that a litigation could be compromised only by
submitting terms thereof to the Court seized of the matter.
Parties to the lis are free to settle the matter out of Court.
Even after settlement, parties do not appear before the Court
and allow the proceedings to be dismissed for want of
prosecution. In the present case, a compromise pursis was
submitted for withdrawal of the appeal. Be that as it may.
This Court is neither endorsing the compromise nor enforcing
the same. The factum of compromise, however, is viewed to
hold the defendant – AMC to have diluted its stand on the
decision of cancelling the lease agreement for illegality
committed by the plaintiff firm and/or its sister concern.
In view of the above, the substantial questions of
law are answered accordingly.
36. During hearing of this appeal, the learned counsel
submitted that, the appellant firm is ready to pay rent/ lease
money @ Rs.15/- per sq.mtr. Since for all the aforesaid
reasons, this Court is inclined to allow the appeal, it proposes
to see that the AMC gets enhancement in the rent since the
appellant firm itself offered to pay the same. It shall,
however, not be misconstrued that, this Court expects the
AMC to perform its further part of the terms of compromise.
The appeal, therefore, succeeds.
O R D E R
(i) The Second Appeal is allowed.
(ii) The impugned decree dated 14/1/2022, passed by the
District Judge-11, Aurangabad in Regular Civil Appeal
No.254/2019 is hereby set aside.
(iii) The decree dated 9/9/2019, passed by the learned Civil
Judge, Senior Division (Corporation Court), Aurangabad in
Regular Civil Suit No.119/2015 is restored on condition of the
plaintiff/ appellant – firm to pay rent/ lease money @ Rs.15/-
per sq.mtr.
(iv) In view of disposal of the Second Appeal, Civil
Application No.8534/2022 stands disposed of.
( R. G. AVACHAT, J. )
On request of learned counsel for the Aurangabad
Municipal Corporation, operation of this order to stand stayed
for the next eight (8) weeks.
( R. G. AVACHAT, J. )
No comments:
Post a Comment