Sunday, 20 February 2022

Whether court can enforce old contract if new contract is nullity?(Doctrine of Novation)

 Nearly a century and a quarter ago, one finds this clear exposition of the principle of novation, in the judgement of the Court of the Judicial Commissioner at Nagpur in Ganpat v. Mahadeo  1925 Nag 26 :

“Where the question is whether one party is set free by the

action of the other, the matter for consideration is whether the

acts or conduct of the one do or do not amount to an

intimation of an intention to abandon and altogether to refuse

performance of the contract. The true question is whether the

acts and conduct of the party evince any intention no longer

to be bound by the contract: Mersay Steel and Iron

Company v. Naglir Benzon & Co. 9 A.C. 434 General Bill

Posting Co v. Atkinson (13). The Court requires as clear

evidence of the waiver as of the existence of the contract

itself and will not act upon less: Carolan v. Brabazon (1900)

A.C. 118 = 78 L.J.; C.H. 77=99 L.T. 913 = 25 T.L.R. 173.

What is then required is that an abandonment of the old

agreement, must be clearly made out. There must be clear

and precise evidence of a mutual intention to determine and

abandon the contract: Mathura Mohan Saha v. Ram

Kumar Saha [1946] 43 Cal. 700=23 C.L.J. 26 = 30 I.C.

305: 20 C.W.N. 370. Where the intention to substitute a new

contract is frustrated by the fact that the new contract is a

nullity, the original contract may be enforceable: see Har

Chandi Lal v. Sheoraj Singh 3 J & L 200 = 9 Ir. & E. 121.

Much more so, where the agreement itself is a contravention

of the statute and does not ripen into a contract in the legal

sense of the term.”

(Emphasis supplied)

A coordinate Bench of this Court has held, recently in Knowledge

Podium Systems Pvt Ltd v. S.M. Professional Services Pvt Ltd26,

that “a novation takes place only when there is a complete substitution of a new contract in place of the old”.

 IN THE HIGH COURT OF DELHI AT NEW DELHI

Pronounced on: 22nd October, 2021

IAs 6433/2020 & IA 7643/2020 in

CS(COMM) INFRA 1/2020

M/S GROVY INDIA LTD Vs BALBIR SINGH

CORAM:

HON'BLE MR. JUSTICE C. HARI SHANKAR

Dated: 22.10.2021

1. On 4th August, 2020, while issuing summons in CS (Comm)

(Infra) 1/2020, IA 6433/2020, filed by the plaintiff under Order

XXXIX Rules 1 and 2 of the Code of Civil Procedure, 1908 (CPC),

was also taken up for preliminary hearing. Ad interim injunction was

granted, in favour of the plaintiff, restraining the defendant from

transferring, alienating, encumbering or further creating any third

party rights in respect of the suit property located at F-6, Kailash


Colony, New Delhi, or carrying out any further alteration in the suit

property.

2. The defendant filed IA 7643/2020, for vacating the aforesaid ad

interim order.

3. Arguments were heard on IA 6433/2020 and IA 7643/2020,

which are being disposed of, by this order.

Facts, as per the plaint

4. The dispute relates to a Property Development Agreement

(“PDA”), dated 14th January, 2020, executed between the plaintiff and

the defendant. The defendant has admitted this document. Clauses 2,

3, 4, 6, 14 and 19 of the PDA read thus:

“2. That the DEVELOPER shall demolish the existing

structure on the said plot of land and develop, construct and/or

build a building consisting of Basement, Stilt, Ground Floor,

First Floor, Second Floor and Third Floor with terrace, at its

own costs and expense.

3. That the DEVELOPER shall develop, construct and

complete the Building at its own costs and expenses after

procuring the requisite permissions, sanctions and approvals

for development construction and completion of the said

building on the said plot at DEVELOPER's cost.

4. That it has been clearly agreed between the parties that the

malba realised from the demolition of the existing structure of

the said property shall belong to the DEVELOPER who shall

have full right to sell the same and receive the proceeds

thereof, without any claim or right of the OWNER in the

same.

6. That in addition to the DEVELOPER incurring the

entire costs and expenses etc. for the construction, will pay a

sum of Rs. 49,00,000/- (Rupees Forty Nine Lakhs Only) to

the OWNER as the total consideration against the rights in the

property to be transferred in favour of the DEVELOPER or its

nominee/s. The abovesaid amount has been paid by the

DEVELOPER to the OWNER, in the following manner:

Rs.4,00,000/- (Rupees Four Lakhs Only) vide cheque

no. 406161 drawn on Axis Bank dated 14/01/2020.

The receipt of which the OWNER hereby admits and

acknowledges. The balance sum of Rs. 45,00,000/-

(Rupees Forty Five Lakhs) shall be made will be paid

by the DEVELOPER to the OWNER. at the time of

registration of the sale documents such as Agreement

to Sell, General Power of Attorney, Will, Affidavits

etc. on or before 5th February, 2020 as the full and final

settlement and discharge.


14. That in view of the above arrangement arrived at

between the parties hereto and in lieu of the DEVELOPER (a)

re-developing the said property at its own cost using its

infrastructure facilities, Man Power, Skill & expertise (b)

paying the aforesaid amount/consideration to the OWNER.

The parties shall be shall be entitled to the following portions

of the newly constructed building as under:

OWNER'S ALLOCATION

i) ENTIRE BASEMENT

ii) ENTIRE GROUND FLOOR

iii) ENTIRE FIRST FLOOR

iv) ENTIRE SECOND FLOOR

v) 77.5% SHARE/PORTION OF THE ENTIRE

STILT AREA FOR CAR PARKING AND

COMMON W.C. THEREIN

vi) USE OF COMMON AREAS, FACILITIES

AND SERVICES

vii) 77.5% UNDIVIDED, INDIVISIBLE AND

IMPARTIBLE OWNERSHIP RIGHTS IN

THE PLOT OF LAND MEASURING 531-

6/10 SQ. YDS.

DEVELOPER'S ALLOCATION

i) ENTIRE THIRD FLOOR

ii) ENTIRE TERRACE OVER AND ABOVE

THE ENTIRE THIRD FLOOR

iii) 22.5% SHARE/PORTION OF THE

ENTIRE STILT AREA WITH

INDEPENDENT BAY WITH SEPARATE

GATE FOR CAR PARKING AND

COMMON W.C. THEREIN (As per

attached plan)

iv) USE OF COMMON AREAS, FACILITIES

AND SERVICES

v) 22.5% UNDIVIDED, INDIVISIBLE AND

IMPARTIBLE OWNERSHIP RIGHTS IN

THE PLOT OF LAND MEASURING 531-

6/10 SQ. YDS.

19. The DEVELOPER and the OWNER shall be entitled

to sell, transfer. convey and assign their respective portions to

any prospective buyer and to receive the sale proceeds in

respect thereof, in their respective names, before, during or

after the completion of the construction, without any

objection or hindrance by the other. Further the

DEVELOPER and the OWNER shall be fully entitled to enter

into any Agreement(s) for the sale/ booking of their

respective allocations in the newly constructed building and

shall be entitled to accept cash/cheque in their respective

names. Further the OWNER hereby agree to confirm, execute

or enter into Agreement. if required by the DEVELOPER,

between the OWNER, DEVELOPER and the prospective

purchaser of the portion(s) falling to the share of the

DEVELOPER.”


5. Clause 6 of the PDA required the plaintiff to pay, to the

defendant, ₹ 49 lakhs. Of this, the payment of an amount of ₹ 4 lakhs,

vide cheque dated 14th January, 2020, stands acknowledged in the said

Clause itself. Clause 6 envisaged payment of the remainder of ₹ 45

lakhs “at the time of registration of the said documents such as the

Agreement to Sell, General Power of Attorney, Will, Affidavits etc.

on or before 5th February, 2020 as the full and final settlement and

discharge”. Out of this amount, according to the plaintiff, TDS of ₹

2,49,000/– and a further amount of ₹ 1 lakh, payable by the defendant

to the plaintiff as per an “Agreement for Construction”, to be executed

subsequently, were deductible, resulting in the net amount payable by

the plaintiff to the defendant reducing to ₹ 43,51,000/–. This amount,

according to the plaintiff, was offered, by way of a crossed cheque, to

the defendant, on 31st January, 2020, whereupon further documents, in

the form of an Agreement to Sell (ATS), Agreement for Construction

(AFC), General Power of Attorney (GPA), a receipt for the advance

payment, Will of the defendant, an affidavit by the Defendant

recognising creation of title interest of the plaintiff in the suit property,

a Power of Attorney by the defendant and possession letter, were

executed.

6. The defendant denies the offer of ₹ 43,51,000/–, by the plaintiff

to the defendant, as well as the execution of all the aforesaid

documents.

7. The plaintiff alleges that it was only at this stage that the

defendant informed the plaintiff that the suit property was mortgaged

with the Standard Chartered Bank (“the Bank”), thereby evidencing

that Recitals H and I in the PDA were untrue.

8. I may note, even at this juncture, that the defendant, having

admitted the PDA, has not chosen to deny the fact that the recital, in

the PDA, regarding the suit property being unencumbered, was not

correct. All that the defendant pleads, by way of a defence, is that,

during the course of discussions prior to execution of the PDA, the

plaintiff had been informed of the fact that the suit property stood

encumbered with the Bank, and that the defendant “blindly” signed

the PDA, “believing” that it was in line with the discussions that had

taken place prior thereto.

9. On 23rd March, 2020, the plaintiff wrote to the defendant,

asserting the above facts and, further, that, during the meeting which

took place on 10th February, 2020 (when, according to the plaintiff, it

had handed over, to the defendant, a cheque for ₹ 43,51,000/–), it was

mutually decided that the aforesaid documents (the ATS, AFC, and

other documents) would be exchanged with the plaintiff on receipt of

a No Objection Certificate (NOC) from the Bank. The letter alleged

that, despite this understanding, when the plaintiff met the defendant

on 12th March, 2020, the defendant refused to obtain the NOC from

the Bank or part with the original documents and threatened, instead,

to forfeit the advance paid by the plaintiff and to enter into an

agreement with another builder. The plaintiff, in the circumstances,

called upon the defendant to perform his part of the PDA, by

producing the original documents of the suit property, registering the

said documents such as the ATS, GPA, Will, PoA, affidavit and

possession letter in favour of the plaintiff, undertaking, in the bargain,

to comply with all its obligations under the PDA and pay the entire

remaining consideration. The plaintiff asserts that it had, thereby,

expressed its readiness and willingness to comply with its

responsibilities under the PDA.

10. The defendant responded, through Counsel, on 4th May, 2020,

alleging that, apart from an initial payment ₹ 4 lakhs, the remaining

amount of ₹ 45 lakhs had neither been paid, nor offered, by the

plaintiff to the defendant on or before 5th February, 2020 or even till

the date of the said communication. The plaintiff’s assertion that it

had offered, to the defendant, a cheque for ₹ 43,51,000/– was

categorically denied. Rather, alleged the defendant, the plaintiff was

circulating messages, offering the suit property for sale, concealing

the entitlements of the defendant. In view of the alleged breaches of

the PDA by the plaintiff, the defendant asserted that it had forfeited

the advance paid by the plaintiff.

11. It is in these circumstances that the plaintiff moved this Court

by means of the present suit.

12. The suit prays thus:

“Wherefore, in the light of the facts and circumstances as

aforementioned, it is humbly prayed that this Hon’ble Court

may be pleased to:

I. Pass a decree of Specific Performance and

Mandatory Injunction in favour of the Plaintiff and

against the Defendant, directing the Defendant to

perform his obligations as per the Property

Development Agreement dated 14.01.2020 including

handing over the peaceful possession of the said

premises to the Plaintiff, produce the original property

papers, hand over all the executed documents, and

further execute all necessary documents to fulfil the

contemplated terms of the Property Development

Agreement dated 14.01.2020.

II. Pass a decree of Specific Performance and

Mandatory Injunction directing the Defendant to seek a

discharge over the mortgage on the said premises, in

the event such a mortgage exists;

III. Pass a decree of Permanent Injunction

restraining the Defendants, their agents, supporters and

assigns from transferring, alienating, encumbrancing

(sic encumbering) or creating any further third-party

rights in any manner whatsoever in respect of the said

premises;

IV. Alternatively, direct the Defendant to return the

advanced payment and pay damages to the tune of ₹

2,00,00,100/– suffered by the plaintiff;

V. Award costs in favour of the Plaintiff;

VI. Pass such or other reliefs/order as this Hon’ble

Court may deem fit and proper in the circumstances of

the case and thus render justice.”

Rival Contentions

13. Mr. Rajiv Garg, learned Counsel for the defendant, has opposed

grant of interim relief to the plaintiff, on the following grounds:

(i) The PDA was unregistered and insufficiently stamped

and could not, therefore, confer any enforceable right on the

plaintiff.


(ii) Specific performance of the PDA could not be ordered by

the Court, in view of Section 14(1)(b) of the Specific Relief

Act, 19631. Reliance was placed, for the purpose, on the

judgment of the Supreme Court in Vinod Seth v. Devinder

Bajaj2 and of this Court in Prem Kumar Bansal v. Ambrish

Garg3.

(iii) The PDA stood novated, within the meaning of Section

624 of the Indian Contract Act, 1872 by the documents alleged,

by the plaintiff, to have been executed later, such as the ATS,

AFC, etc.

(iv) The plaintiff’s assertion of readiness and willingness to

perform his part of the PDA was a mere eyewash, as it did not

have the financial wherewithal to comply with its obligation.

Reliance was placed, for this purpose, on the Axis Bank

statement of the plaintiff.

(v) In fact, the plaintiff had, till date, paid only ₹ 4 lakhs, out

of the total amount payable by the plaintiff under the PDA or

even under Clause 6 thereof. Specific performance of the PDA

could not be claimed on payment of such a small amount.

1 14. Contracts not specifically enforceable. – The following contracts cannot be specifically enforced,

namely: -

(b) a contract, the performance of which involves the performance of a continuous duty

which the court cannot supervise;"

2 (2010) 8 SCC 1

3 230 (2016) DLT 360

4 62. Effect of novation, rescission and alteration of contract. – If the parties to a contract agree to

substitute a new contract for it, or to rescind or alter it, the original contract need not be performed.

(vi) The plaintiff knew of the fact that the suit property was

mortgaged with the Bank at the time of execution of the PDA,

having been made aware of the mortgage during the course of

discussions prior to execution of the PDA. By its letter dated

23rd March, 2020, this fact was condoned and waived by the

plaintiff.

(vii) The defendant had signed the PDA blindly, believing that

it was in accordance with the discussions which had preceded

its execution.

14. To these objections, Mr. Aditya Wadhwa, learned Counsel for

the plaintiff, responded thus:

(i) As the PDA was not a contract for sale, and did not

create, by itself, any right or title, it was not required to be

registered, by virtue of Section 17 of the Registration Act5.

5 17. Documents of which registration is compulsory. –

(1) The following documents shall be registered, if the property to which they relate is situate

in the district in which, as if they had been executed on or after the date on which, Act No. XVI of

1864, or the Indian Registration Act, 1866, or the Indian Registration Act, 1871, or the Indian

Registration Act, 1877, or this Act came or comes into force, namely: -

(b) other non-testamentary instruments which purport or operate to create, declare,

assign, limit or extinguish, whether in present or in future, any right, title or interest,

whether vested or contingent, of the value of ₹ 100 or upwards, to or in immovable

property;

(c) non-testamentary instruments which acknowledge the receipt of payment of any

consideration on account of the creation, declaration, assignment, limitation or extinction

of any such right, title or interest;

*****

(2) Nothing in clauses (b) and (c) of sub- section (1) applies to –

*****

(v) any document other than the documents specified in sub-section (1A) not itself

creating, declaring, assigning, limiting or extinguishing any right, title or interest of the

value of one hundred rupees and upwards to or in any immovable property, but merely

creating a right to obtain another document which will, when executed, create, declare,

assign, limit or extinguish any such right, title or interest;

(ii) Having admitted the PDA, the defendant could not be

heard to contend that it was insufficiently stamped, as held in

Shyamal Kumar Roy v. Sushil Kumar Aggarwal6 and by this

Court in Sudir Engineering Co. v. Nitco Roadways Ltd7.

That apart, Article 23A of the Stamp Act was inapplicable to

the PDA. It was merely a contract envisaging sale of property,

not a contract selling the property as such. It did not

contemplate transfer of possession; ergo, Article 23A of the

Stamp Act would also not apply. Reliance was placed on the

judgements of the Supreme Court in Omprakash v.

Laxminarayan8 and Avinash Chauhan v. Vijay Mishra9.

Rather, stamp duty was payable, on the PDA, under Article 5 of

the Stamp Act.

(iii) Besides, injunction could be granted even on an

insufficiently stamped document, as held by the High Court of

Calcutta in GTZ (India Pvt Ltd) v. Power Electronics

Engineers10 and by the High Court of Bombay in Sanjay v.

Vishnupant11.

(iv) The PDA was not incapable of specific performance, for

the following reasons:

6 (2006) 11 SCC 331

7 1995 (34) DRJ 86

8 (2014) 1 SCC 618

9 (2009) 2 SCC 532

10 2009 SCC OnLine Cal 2162

11 (2007) 6 Mah LJ 550 : 2007 SCC OnLine Bom 610

(a) The PDA was not a mere construction agreement,

but also conferred ownership rights on the plaintiff.

(b) The PDA itself contained in a recital that breach of

its terms would entitle the aggrieved party to enforce the

PDA by suing for specific performance.

(c) The PDA contained detailed plans, layouts and

constructions for redevelopment of each floor of the suit

property. It did not, therefore, contemplate continuous

performance of mutual obligations, but was targeted at a

final result. Such a contract was not excepted from

specific performance under Section 14(b) of the Specific

Relief Act.

Mr. Wadhwa placed reliance on the judgements of the Supreme

Court in Suraj Lamps & Industries Pvt Ltd v. State of

Haryana12 and Sushil Kumar Agarwal v. Meenakshi

Sandhu13, the High Court of Bombay in Shapoorji Pallonji v.

Jignesh Shah14 and the House of Lords in Co-operative

Insurance Society Ltd v. Argyll Stores15. Vinod Seth2, it was

submitted, involved a vague oral agreement whereas, in Prem

Kumar Bansal3, the obligations, sought to be enforced, were

required to be performed by both parties; moreover, the

12 (2012) 1 SCC 656

13 (2019) 2 SCC 241

14 (2013) 6 Bom CR 575 : 2013 SCC OnLine Bom 709

15 1998 AC 1

judgment was rendered under the pre-amended Specific Relief

Act.

Analysis

15. The interim relief that was granted by this Court, and of which

the defendant seeks vacation, was a restraint against alienation or

creation of third party rights, or for carrying out any further alteration

in the suit property. The three considerations, which govern every plea

for grant of interim injunction under Order XXXIX of the CPC, are

the existence of a prima facie case, balance of convenience and the

likelihood of irreparable loss were injunction not to be granted. All

three considerations have to coalesce, for injunction to be justified.

16. The plaintiff has, in this suit, sought specific performance of the

PDA and thereby a direction to the defendant to hand over peaceful

possession of the suit property to the plaintiff, produce the original

property papers, handover all the executed documents, and further

execute all such other necessary documents to fulfil the contemplated

terms of the PDA. Additionally, a direction to the defendant, to have

the mortgage, in respect of the suit property, redeemed, has also been

sought.

17. Balance of convenience and irreparable loss:

17.1 The plaintiff seeks specific performance of an agreement

relating to immovable property, whereunder the plaintiff claims that

rights enure in its favour. In such a case, unless the claim is found to

be, prima facie, entirely insubstantial, considerations of equity and the

interests of justice would, classically, justify preservation of status

quo in respect of the corpus of the dispute. This is simply because, if,

ultimately, the case of the plaintiff is found to be without merit, the

defendant could deal with the property as it chooses, and also be

adequately recompensed for the prejudice, if any, which has been

caused by its inability to do so in the interregnum whereas, if the

status of the property, whether in respect of title or possession, alters

during the pendency of the lis, the resultant prejudice to the plaintiff

might well-nigh be irremediable. Principles of balance of

convenience too, therefore, normally justify maintenance of the status

quo during the pendency of the litigation.

17.2 Having said that, it is also true that the plaintiff cannot treat

itself as entitled to any interim relief unless it establishes the

existence, in its favour, of a prima facie case. Sans a prima facie

case, no interim relief can be granted to a litigant before the Court,

howsoever serious the consequence of refusal of the prayer might be.

17.3 Indeed, learned Counsel for the parties did not address any

submissions, to this Court, on the aspect of balance of convenience

and irreparable loss. Arguments were confined to the aspect of

entitlement, of the plaintiff, to the relief ultimately sought in the

plaint.

18. Prima facie merits of the case:

18.1 Mr. Garg, learned Counsel for the defendant, has not disputed

the fact that, contrary to recitals H and I in the PDA, the suit property

was, in fact, mortgaged with the bank even at the time when the PDA

was executed. Clearly, therefore, the recitals H and I in the PDA were

untrue. This fact, even by itself, tilts the equities of the case strongly

in favour of the plaintiff.

18.2 There is no material, whatsoever, to support Mr. Garg’s

contention that, prior to executing of the PDA, the defendant was

made aware of the fact that the suit property was mortgaged with the

Bank. Equally, his contention that the defendant had blindly signed

the PDA, believing the PDA to be in line with the discussions which

had purportedly taken place prior to its execution, is also too facile to

be believed at this prima facie stage. Any such case, if at all, would

have to be established by the defendant only consequent on trial. For

the time being, the position that stares the Court in the face is that the

PDA wrongly stated that the suit property was unencumbered, without

disclosing the fact that it stood mortgaged with the Bank.

19. In the face of all these facts and considerations, the Court is

only required to examine whether the submissions of Mr. Garg are

such as to disentitle the plaintiff to an interlocutory injunction qua

maintenance of status quo regarding the suit property, or whether a

case has been made out, to justify vacation of the injunction already

granted.

20. Re. PDA being unregistered:

20.1 Mr. Garg has sought to question the enforceability of the PDA

on the ground that it is unregistered and insufficiently stamped. As

such, he contends that it can confer no enforceable right on the

plaintiff.

20.2 It is necessary, at the first instance, to examine the PDA itself.

20.3 The PDA refers to the defendant Balbir Singh as the “Owner”

and the plaintiff Grovy India Ltd the “Developer”. Clauses A to E of

the PDA set out the manner in which the defendant became the sole,

absolute and exclusive owner of the suit property. Clause F evinces

the desire of the defendant to get the suit property

redeveloped/reconstructed after demolition of the existing structure,

for which the defendant approached the plaintiff. The plaintiff is

required, as per the said Clause, to develop the suit property on behalf

of the defendant at the plaintiff’s cost. Clause H contains the

representation that the suit property is free from all sorts of

encumbrances, charges, liens, claims, lease, prior agreements and

disavows the existence of any right, title or interest in the suit property

of any person other than the owner. The purportedly unencumbered

nature of the suit property is further emphasized in Clause I. Sub

clause (h) of Clause I reads thus:

“(h) That in case any of the representations/assurances

made by the OWNER are found to be untrue and/or if the

whole or any portion of the said DEVELOPER's Allocation

(fully described below) is ever taken away or goes out from

the possession of the DEVELOPER on account of any legal

defect in the ownership and title of the OWNER then the

OWNER will be liable and responsible to make good the loss

suffered by the DEVELOPER and shall keep the

DEVELOPER saved harmless and indemnified against all

such costs, damages, losses suffered by the DEVELOPER,

from his properties both movable and immovable.”

20.4 Clause J evinces the agreement, between the plaintiff and the

defendant, to develop, construct and build a fresh building on the area

occupied by the suit property, for which purpose the PDA was being

executed.

20.5 The substantive clauses of the PDA follow.

20.6 Clause 1 states that the defendant had got the building plans

sanctioned from the concerned authorities. Clauses 2, 3 and 5 set out

the duties and responsibilities of the plaintiff as developer. Clause 2

requires the plaintiff to demolish the existing structure on the suit

property and to develop/construct a building consisting of basement,

stilt, ground floor, first floor, second floor and third floor with terrace,

at the plaintiff’s cost and expense. Clause 3 requires the plaintiff to

procure the requisite permissions, sanctions and approvals for

executing the construction and completion of the building. Clause 5

records the plaintiff’s undertaking to modify the building plans in

accordance with the building bye-laws as applicable from time to time

and to make full efforts to obtain permission for the maximum area to

be covered on the suit property. It further records the requirements

that the total FAR (Floor Area Ratio) sanctioned on the plot of land

comprising the suit property is required to be divided equally on all

four floors. Clause 4 entitles the plaintiff to ownership of the malba

resulting from demolition of the structure existing on the suit property

as well as to sell the malba and appropriate the sale proceeds.

20.7 Clause 6 sets out the financial liabilities of the plaintiff under

the PDA. It requires the plaintiff to, apart from incurring the entire

costs and expenses for construction of the new building, additionally

pay a sum of ₹ 49 lakhs to the defendant as total consideration against

the rights in the property to be transferred in favour of the plaintiff.

The payment of ₹ 4 lakhs, out of the said amount, vide cheque dated

14th January, 2020, by the plaintiff to the defendant has also been

recorded. Apropos payment of the balance amount, Clause 6 requires

the payment to be made by the plaintiff to the defendant “at the time

of registration of the sale documents such as Agreement to Sell,

General Power of Attorney, Will, Affidavit etc. on or before 5th

February, 2020 as the full and final settlement and discharge”.

20.8 Clause 7 records the consent, of the defendant, to the plaintiff

carrying out necessary acts including demolition and reconstruction,

in accordance with the preceding terms and conditions of the PDA.

Clause 9 empowers the plaintiff to engage or employ architects to

carry out the construction at its own cost and expense and to apply for

permissions, sanctions and approvals to the municipal authorities.

Clause 10 defrays all expenses for carrying out construction,

development and completion of building, including architects’ charges

and fees, to the account of the plaintiff. This aspect is reiterated in

Clause 12.

20.9 Clause 11 requires the quality of construction of the building to

be of good standard.

20.10 Clauses 13 and 14 set out the allocation of the portion

reconstructed building, which would fall to the share of the plaintiff

and the defendant. Clause 15 further grants exclusive ownership and

user rights of the entire terrace over and above the third floor of the

property including right of further constructions thereon, to the

plaintiff. Clause 16 requires the plaintiff to install a lift in the building,

for common use of the owners/occupiers at all floors, and further

stipulates that the maintenance costs of the lift and of electricity for

use of the lift would be proportionately shared by owners/occupiers of

the building.

20.11 Clause 17 is a standard indemnity clause, indemnifying the

plaintiff from any liabilities arising in respect of the suit property,

during implementation of the PDA.

20.12 Clause 18 requires the defendant to pay all outstanding charges

and dues in respect of the suit property including house tax, property

tax and water and electricity charges, while retaining liability, towards

water and electricity charges, borne during the period of construction,

with the plaintiff. Consequent on completion of construction,

however, Clause 18 stipulates that house tax, water and electricity

charges would be borne by the defendant in respect of their respective

allocations in the building.

20.13 Clause 19 entitles the plaintiff and the defendant to sell,

transfer, convey and assign their respective portions in the building to

be constructed to any prospective buyer, and to receive sale

proceedings in respect thereof, either before, during or after the

completion of the construction. The plaintiff and the defendant are

also entitled, by the said clause, to enter into agreements for

sale/booking of their respective allocations in the newly constructed

building and accept payments in respect thereof.

20.14 Clause 20 records the undertaking of the defendant to join in the

execution of all necessary documents, to accord legal title to the

buyers of any flats or portions of the plaintiff’s share in the

constructed building, without further payment. Clause 21 requires the

building to be completed within 24 months of the date of handing over

of possession of the suit property to the plaintiff, subject to force

majeure, failing which Clause 22 requires the plaintiff to pay, to the

defendant, ₹ 3 lakhs per month as penalty.

20.15 Clause 23 indemnifies the defendant against any accident or

claim from any person, including neighbours, on account of the

construction of the proposed building, and renders the plaintiff solely

responsible in that regard. Clause 24 clarifies that the PDA would not

constitute a partnership, between the plaintiff and the defendant. In the

event of any deviation from the agreed specifications, Clause 25

requires the defendant to inform the plaintiff, who would rectify the

deviation at its own costs/arrangements, but otherwise proscribes any

interference, or obstruction, by the defendant, with the execution and

completion of the work of development and construction of the new

building. Financial liabilities, arising out of the sale of the respective

shares of the suit property, falling to the lot of the plaintiff and the

defendant, are, by Clause 26, to be borne by them.

20.16 Clauses 28 to 31 deal with the rights to use common areas of

the suit property during construction. Clause 32 requires that, upon

completion of construction, the plaintiff would first hand over

possession of the defendant’s share, complete in all respects, by way

of a written intimation, and requires the defendant to take possession

of his share within 15 days as of the said offer. Failure, on the part of

the defendant, to take possession within the said period of 15 days

would result in possession being deemed to have been handed over to

the defendant.

20.17 Clause 32 inhibits the plaintiff from assigning or nominating the

PDA in favour of any third party, and contains the following specific

recital:

“The contract being personal in nature and dependent on

respective rights and obligations of the parties and thus is not

in the nature of contract for sale, as defined U/s 54 of the

Transfer of Property Act and not required to be registered U/s

17 (1) (A) of the Registration Act. 1908.”

(Emphasis supplied)

20.18 Clause 33 requires GST to be borne by the plaintiff. Clause 34

states that the PDA is irrevocable under all circumstances and Clause

35 entitles either party to, in the event of infringement, by the opposite

party, of any terms or conditions of the PDA, have the PDA enforced

through court by claiming specific performance.

20.19 As already noted, Clause 32 of the PDA itself states that it is

not in the nature of a contract for sale within the meaning of Section

54 of the Transfer of Property Act and that it is, therefore, required to

be registered under Section 17 (1) of the Registration Act.

20.20 Section 17(1)(b) of the Registration Act requires registration of

instruments which create right, title or interest in immovable property.

The various Clauses of the PDA, holistically read, merely set out the

obligations of the plaintiff and the defendant, and the rights and the

entitlements which flow therefrom. Clause 6 specifically envisages,

after completion of construction, execution of documents such as

agreement to sell, general power of attorney, will, affidavit, etc.,

which are referred to, in the said clause, specifically as “the sale

documents”. It cannot, therefore, prima facie, be said that transfer of

right or ownership in the suit property was conveyed by the PDA

itself, as would require its registration, mandatorily, under Section

17(1) of the Registration Act.

20.21 The objection of Mr Garg to the unregistered nature of the PDA

as a ground to non-suit the plaintiff from claiming interlocutory

reliefs, therefore, fails to impress.

21. Re: objection regarding insufficient stamping

21.1 Mr. Garg has sought to contend that the PDA was required to be

stamped in accordance with Article 23A of Schedule 1 of the Stamp

Act and that, not having been so stamped, the plaintiff could not

derive any rights therefrom. Article 23A of Schedule 1 of the Stamp

Act which provides for the requisite stamp duty on instruments reads

thus:

Description of instrument Proper Stamp Duty

23A. Conveyance in the nature

of Part Performance—

Contracts for the transfer of

immovable property in the nature

of part performance in any Union

territory under section 53A of the

Transfer of Property Act, 1882

(4 of 1882).

Ninety per cent of the duty as a

Conveyance (No. 23).

21.2 “Conveyance” is defined, in clause (10) of Section 2 of the

Stamp Act, thus:

“(10) Conveyance – “Conveyance” includes a conveyance

on sale every instrument by which property, whether

moveable or immovable, is transferred inter vivos and which

is not otherwise specifically provided for by schedule I”

21.3 Omprakash8, on which Mr. Wadhwa relies, precisely dealt

with the interpretation of this clause. In that case, specific performance

was sought, by the respondent before the Supreme Court, of an

agreement to sell. Para 11 of the report records that the agreement to

sell acknowledged “payment of the part of consideration money and

further giving actual physical possession to the purchaser by the

seller”. The question before the Supreme Court was whether the

agreement to sell was a “conveyance”, which was required to be

stamped in accordance with Article 23 of Schedule I-A of the Stamp

Act. Referring to the definition of “conveyance” in Section 2(10), the

Supreme Court held, in para 13 of the report, that it was “evident that

an instrument by which movable and immovable property is

transferred, comes within the expression “conveyance” ”. Transfer, it

was further held, required payment of the consideration in whole or in

part and handing over of the possession of the property. In this

context, the Supreme Court held that the recitals in the

document/deeds were relevant to determine whether the document was

required to be stamped.

21.4 Applying the said principle, it cannot be said that the PDA is a

document which conveys title in property, or results in transfer, by

handing over of possession against payment of consideration.

21.5 Three decisions of this Court further illumine this path.

21.6 A Division Bench of this Court has clearly held as follows, in

Pawandeep Singh v. Gurdeep Singh Virdi16:

“19. The law on this aspect is clear. An unregistered

Agreement to Sell cannot be used as a shield under Section 53

A of the TPA since Section 17(1-A) of the Registration Act,

1908 makes the documents containing a contract to transfer

for consideration, any immovable property for the purpose of

Section 53 A, compulsorily registrable. If such documents are

not registered, they shall have no effect for the purposes of

Section 53 A. For purposes of ready reference, Section 17 of

the Registration Act, 1908 is reproduced below:—

17. Documents of which registration is compulsory-

16 2019 SCC OnLine Del 9495

(1) The following documents shall be

registered, if the property to which they relate is

situate in a district in which, and if they have

been examined on or after the date on which,

Act XVI of 1864, or the Indian Registration Act,

1866 (20 of 1866), or the Indian Registration

Act, 1871 (8 of 1871), or the Indian Registration

Act, 1877 (3 of 1877), or this Act came or

comes into force, namely –

(a) instruments of gift of immovable

property;

(b) other non-testamentary

instruments which purport or operate to

create, declare, assign, limit or

extinguish, whether in present or in

future, any right, title or interest, whether

vested or contingent, of the value of one

hundred rupees and upwards, to or in

immovable property;

(c) non-testamentary instruments

which acknowledge the receipt or

payment of any consideration on account

of the creation, declaration, assignment,

limitation or extinction of any such right,

title or interest; and

(d) lease of immovable property from

year to year, or for any term exceeding

one year, or reserving a yearly rent;

(e) non-testamentary instruments

transferring or assigning any decree or

order of a Court or any award when such

decree or order or award purports or

operates to create, declare, assign, limit

or extinguish, whether in present or in

future, any right, title or interest, whether

vested or contingent, of the value of one

hundred rupees and upwards, to or in

immovable property:

Provided that the State Government may,

by order published in the Official Gazette,

exempt, from the operation of this sub-section

any leases executed in any district, or part of a

district, the terms granted by which do not

exceed five years and the annual rents reserved

by which do not exceed fifty rupees.

(1-A) The documents containing contracts to

transfer for consideration, any immovable

property for the purpose of Section 53-A of the

Transfer of Property Act, 1882 (4 of 1882), shall

be registered if they have been executed on or

after the commencement of the Registration and

Other Related Laws (Amendment) Act, 2001

and, if such documents are not registered on or

after such commencement, then, they shall have

no effect for the purposes of the said Section 53-

A.”

20. The remedy, if any, for the appellant no. 1 would have

been to sue for specific performance as Section 49 of the

Registration Act, 1908 states that a suit for specific

performance can be initiated on the basis of an unregistered

Agreement to Sell. Section 49 reads as under:

“49. Effect of non-registration of documents required

to be registered. – No document required by Section 17

or by any provision of the Transfer of Property Act,

1882 to be registered shall –

(a) affect any immovable property

comprised therein, or

(b) confer any power to adopt, or

(c) be received as evidence of any

transaction affecting such property or conferring

such power, unless it has been registered:

Provided that an unregistered document

affecting immovable property and required by this Act

or the Transfer of Property Act, 1882, to be registered

may be received as evidence of a contract in a suit for

specific performance under Chapter II of the Specific

Relief Act, 1877 or as evidence of any collateral

transaction not required to be effected by registered

instrument.”

(Emphasis supplied)

21.7 To the same effect, paras 24 and 25 of the judgment of a

coordinate single Bench of this Court in Rishi Raj v. Rakesh

Yadav17, reads thus:

“24. This decision has been followed by a Ld. Single Judge

of this Court in Vinod Kumar v. Ajit Singh18, where the

Court held:

“10. In the instant case, the plaintiff has not sought

relief based on part performance under Section 53A of

the Transfer of Property Act and that being so, Section

17(1A) of the Registration Act, which was only meant

for the provisions of Section 53A of the Transfer of

Property Act, was not attracted and thus, the agreement

did not require registration. Such an agreement falls

under the mischief of Section 17(2)(v) of the

Registration Act, and it itself does not create, declare,

assign, limit or extinguish any right, title or interest in

the property. Rather as held in Sukhwinder

Kaur (supra)19 it creates a right to obtain another

document which will, when executed, create, declare,

assign, limit or extinguish right, title or interest in the

property. Not only this, provisions of Section 49 of the

Registration Act make the position more clear. It

envisages that an unregistered document affecting

immovable property and required by this Act and the

Transfer of Property Act to be registered may be

received as evidence of a contract in a suit for specific

performance under Chapter-II of Specific Relief Act,

1877. As further held in Sukhwinder Kaur (supra), a

conjoint reading of Section 17(2)(v) and proviso of

Section 49 of the Act leaves no room for doubt that

agreement to sell property itself does not create any

17 2018 SCC OnLine 9425

18 (2013) 138 DRJ 324

19 AIR 2012 P&H 97

right or title over the property. It is the sale deed,

which when executed will create such right in the

property. Hence, an agreement to sell is not required to

be registered and the same is receivable in evidence in

a suit for specific performance under Chapter-II of the

Specific Relief Act, 1877.”

25. Based on the above judgments it is clear that it is

permissible in law to seek specific performance of an

unregistered agreement to sell, when possession of the

property has not been handed over. In this case, from the

evidence which has now come on record, it is clear that

physical possession of the property was not handed over to

the Plaintiff at the time of the execution of the documents

dated 6th August, 2013. As per the documents dated

6th August, 2013 no registration was required for the same.”

(Emphasis supplied)

21.8 And again, paras 7 and 8 of the judgment of another coordinate

Bench of this Court in Devender Singh v. Hari Singh20 ruled thus:

“7. Before the first appellate court an issue was raised that

the receipt-cum-agreement to sell dated 22.1.2002 is not

registered and hence cannot be looked into by virtue of

provision of Section 17(1)(a) of the Registration Act, 1908,

however, this contention is unsound, inasmuch as, an

unregistered agreement to sell cannot be looked into only for

seeking benefit of part performance under Section 53A of the

Transfer of Property Act, 1882 in view of Amendment of

Section 53A by Act 48 of 2001 with effect from 24.9.2001,

however, an unregistered agreement to sell can always be a

basis for a suit for specific performance in view of Section 49

of the Registration Act.

8. Learned counsel for the appellant/defendant relied

upon a judgment of a learned Single Judge of the Punjab and

Haryana High Court in the case of Gurbachan

Singh v. Raghubir Singh21, to argue that an unregisterd

agreement to sell cannot be a basis for a suit for specific

performance, however, with utmost respect and humility to

20 2017 SCC OnLine 8036

21 AIR 2010 P&H 77

the learned Single Judge, I cannot agree with the ratio of the

judgment because the ratio of the judgment is against the

direct and categorical language of Section 49 of the

Registration Act which permits an unregistered agreement to

sell for being looked into as a basis in a suit seeking specific

performance. An unregistered agreement to sell cannot be

used only if the same is sought to be used as one for seeking

benefit of Section 53A of the Transfer of Property Act

containing the doctrine of part performance, however, once,

the unregistered agreement to sell is not used for seeking

benefit of the doctrine of part performance under Section 53A

of the Transfer of Property Act, then by virtue of Section 49

of the Registration Act, surely a suit for specific performance

will lie on the basis of unregistered agreement to sell.”

21.9 The plaintiff, in the present case, seeks specific performance of

the PDA. The claim of the plaintiff is not for part performance under

Section 53A of the Transfer of Property Act.

21.10 Following the law laid down in the aforesaid decisions, prima

facie, the submission of Mr. Garg that the suit is not maintainable as

the PDA is unregistered and is insufficiently stamped, cannot pass

muster.

22. Re. Section 14(1)(b) of Specific Relief Act

22.1 Though, in the written submissions tendered by the defendant as

encapsulating the submissions advanced at the Bar, this contention has

not been raised, it was, in fact, argued, and I proceed, therefore, to

deal with it.

22.2 Section 14(1)(b) of the Specific Relief Act completely bars

grant of interlocutory relief as sought by the plaintiff, contends Mr.

Garg. The provision, as it stands today, reads thus:

“14. Contracts not specifically enforceable. – The

following contracts cannot be specifically enforced, namely:-

*****

(b) a contract, the performance of which involves

the performance of a continuous duty which the court

cannot supervise;”

This, however, is the amended avatar of Section 14. Prior to its

amendment by Section 5 of the Specific Relief (Amendment) Act,

2018, Section 14 (to the extent relevant) read as under:

“14. Contracts not specifically enforceable. –

(1) The following contracts cannot be specifically

enforced, namely: –

(d) a contract the performance of which involves

the performance of a continuous duty which the court

cannot supervise.

*****

(3) Notwithstanding anything contained in clause (a) or

clause (c) or clause (d) of sub- section (1), the court may

enforce specific performance in the following cases: –

*****

(c) where the suit is for the enforcement of a

contract for the construction of any building or the

execution of any other work on land:

Provided that the following conditions are fulfilled,

namely: –

(i) the building or other work is described in

the contract in terms sufficiently precise to

enable the court to determine the exact nature of

the building or work;

(ii) the plaintiff has a substantial interest in

the performance of the contract and the interest

is of such nature that compensation in money

for non-performance of the contract is not an

adequate relief; and

(iii) the defendant has, in pursuance of the

contract, obtained possession of the whole or

any part of the land on which the building is to

be constructed or other work is to be executed.”

Prior to its amendment, therefore, Section 14 required, for specific

performance of a contract for the construction of a building, the

contract to describe the building “in terms sufficiently precise to

enable the courts to determine the exact nature of the building or

work”. That requirement is now done away with. Decisions, which

have held a contract for construction of a building or other work not

to be capable of being enforced by way of specific performance on the

ground that the contract is imprecise or vague, relating to causes of

action arising during the currency of the pre-amended Section 14 of

the Specific Relief Act cannot, therefore, prima facie, constitute

valuable precedents, to guide cases arising after Section 14 was

amended.

22.3 Having said that, “a contract, the performance of which

involves the performance of a continuous duty which the court cannot

supervise” still remains impervious to enforcement by way of specific

performance.

22.4 Mr Garg has cited, in support of this submission, the judgement

of the Supreme Court in Vinod Seth2 and of this Court in Prem

Kumar Bansal3 whereas Mr. Wadhwa has relied on the judgment in

Sushil Kumar Agarwal13.

22.5 All the aforesaid decisions relate to the pre-amended Section 14

and involve a consideration, to one extent or the other, of the erstwhile

Section 14(3)(c) of the Specific Relief Act.

22.6 Vinod Seth2:

22.6.1 The issue before the Supreme Court in this case was peculiar, as

is apparent from the opening paragraph of the decision, which reads

thus:

“Leave granted. Heard. The validity of a novel and innovative

direction by the High Court, purportedly issued to discourage

frivolous and speculative litigation is under challenge in this

appeal. To understand the issue, it is necessary to set out the

facts and also extract relevant portions of the plaint and the

impugned orders of the High Court.”

22.6.2 In Vinod Seth2, the appellant Vinod Seth was a builder. He

sued the respondent Devender Bajaj for specific performance of an

alleged oral agreement for “commercial collaboration for business

benefits”, in connection with premises of which Devender Bajaj was

the owner.

22.6.3 The matter came up before a learned Single Judge of this Court

who held that, as the agreement was undocumented, all terms thereof

would have to be established by evidence. As such, the prayer for

specific performance of the agreement would require constant

supervision by the Court, which was difficult. Opining, therefore, that

the suit was unlikely to succeed, the learned Single Judge deemed it

appropriate to indemnify the defendant, in advance, so as to “equalize”

the plaintiff and the defendant. He, therefore, directed the plaintiff to

file an undertaking to pay the defendant a sum of ₹ 25 lakhs in the

event of the plaintiff failing in the suit.

22.6.4 This direction was upheld by the Division Bench of this Court,

compelling the plaintiff to approach the Supreme Court. The main

issue before the Supreme Court was whether a direction to pay the

defendant, in the case of the plaintiff failing to succeed in the suit, a

sum of ₹ 25 lakhs, was sustainable in law.

22.6.5 The Supreme Court ultimately answered this question in the

negative, essentially on the premise that necessary safeguards, against

frivolous suits and their prosecution, were already inbuilt in the CPC,

and the Court could not, even acting ex debito justitiate, innovate and

pass directions which were not envisaged by the CPC. Clearly, this

aspect of the decision in Vinod Seth2 does not concern us in the

present matter.

22.6.6 The Supreme Court, however, expressed its broad agreement

with this Court that, “on the material presently on record, the

likelihood of the appellant succeeding in the suit or securing any

interim relief against the defendant (was) remote”.22 The Supreme

Court went on to set out the reasons for this tentative conclusion. The

first was that it was “doubtful whether the collaboration agreement, as

22 Refer para 11 of the report

alleged by the appellant, (was) specifically enforceable, having regard

to the prohibition contained in Sections 14(1)(b) and (d) of the

Specific Relief Act, 1963”. It was observed that the agreement was

not a usual agreement for sale/transfer, which was enforceable in

nature. In this context, para 15 of the report merits reproduction, thus:

“15. The alleged agreement being vague and incomplete,

requires consensus, decisions or further agreement on several

minute details. It would also involve performance of a

continuous duty by the appellant which the court will not be

able to supervise. The performance of the obligations of a

developer/builder under a collaboration agreement cannot be

compared to the statutory liability of a landlord to reconstruct

and deliver a shop premises to a tenant under a rent control

legislation, which is enforceable under the statutory

provisions of the special law. A collaboration agreement of

the nature alleged by the appellant is not one that could be

specifically enforced. Further, as the appellant has not made

an alternative prayer for compensation for breach, there is

also a bar in regard to award of any compensation under

Section 21 of the Specific Relief Act.”

(Italics and underscoring supplied)

22.6.7 The Court was, therefore, in Vinod Seth2, dealing with a vague,

imprecise and oral agreement. A reading of the decision makes it

clear that the difficulty which, in the opinion of the Court, would arise

in attempting specific performance of such an undocumented

agreement was one of the main considerations which compelled the

Supreme Court to agree with the view of this Court that the agreement

was incapable of specific performance.

22.6.8 In appreciating the law enunciated in Vinod Seth2, the Court

cannot, in my view, proceed unmindful of the nature of the

controversy, and, especially, the agreement, which was before the

Supreme Court. Judgements of courts, including the Supreme Court,

it is trite, are not to be treated as analogous to Euclid’s theorems, and

followed blindly, without appreciating the fact-situation in which they

came to be rendered.23

22.7 Sushil Kumar Agarwal13:

22.7.1 As against this, Sushil Kumar Agarwal13, also by a Bench of

two Hon’ble Judges of the Supreme Court, involved a suit for specific

performance of a written development agreement. It is unnecessary to

delve into the specifics of the disputes in that case. Suffice it to

reproduce paras 18, 19 and 24.3 of the report, which read as under:

18. When a pure construction contract is entered into, the

contractor has no interest in either the land or the

construction which is carried out. But in various other

categories of development agreements, the developer may

have acquired a valuable right either in the property or in the

constructed area. The terms of the agreement are crucial in

determining whether any interest has been created in the land

or in respect of rights in the land in favour of the developer

and if so, the nature and extent of the rights.

19. In a construction contract, the contractor has no interest

in either the land or the construction carried out on the land.

But, in other species of development agreements, the

developer may have acquired a valuable right either in the

property or the constructed area. There are various incidents

of ownership in respect of an immovable property. Primarily,

ownership imports the right of exclusive possession and the

enjoyment of the thing owned. The owner in possession of the

thing has the right to exclude all others from its possession

and enjoyment. The right to ownership of a property carries

with it the right to its enjoyment, right to its access and to

other beneficial enjoyments incidental to it. [B.

23 Refer Union of India v Major Bahadur Singh (2004) 1 SCC 368; Chintels India v Bhayana Builders

Pvt Ltd (2021) 4 SCC 602; Amar Nath Om Prakash v State of Punjab (1985) 1 SCC 345

Gangadhar v. B.G. Rajalingam, (1995) 5 SCC 238, para 6].

Ownership denotes the relationship between a person and an

object forming the subject-matter of the ownership. It consists

of a complex of rights, all of which are rights in rem, being

good against the world and not merely against specific

persons. There are various rights or incidents of ownership all

of which need not necessarily be present in every case. They

may include a right to possess, use and enjoy the thing owned;

and a right to consume, destroy or alienate it. [Swadesh

Ranjan Sinha v. Haradeb Banerjee, (1991) 4 SCC 572] .

An essential incident of ownership of land is the right to

exploit the development, potential to construct and to deal

with the constructed area. In some situations, under a

development agreement, an owner may part with such rights

to a developer. This in essence is a parting of some of the

incidents of ownership of the immovable property. There

could be situations where pursuant to the grant of such rights,

the developer has incurred a substantial investment, altered

the state of the property and even created third-party rights in

the property or the construction to be carried out. There could

be situations where it is the developer who by his efforts has

rendered a property developable by taking steps in law. In

development agreements of this nature, where an interest is

created in the land or in the development in favour of the

developer, it may be difficult to hold that the agreement is not

capable of being specifically performed. For example, the

developer may have evicted or settled with occupants, got

land which was agricultural converted into non-agricultural

use, carried out a partial development of the property and

pursuant to the rights conferred under the agreement, created

third-party rights in favour of flat purchasers in the proposed

building. In such a situation, if for no fault of the developer,

the owner seeks to resile from the agreement and terminates

the development agreement, it may be difficult to hold that the

developer is not entitled to enforce his rights. This of course is

dependent on the terms of the agreement in each case. There

cannot be a uniform formula for determining whether an

agreement granting development rights can be specifically

enforced and it would depend on the nature of the agreement

in each case and the rights created under it.

*****

24.3. In order to determine the exact nature of the agreement

signed between the parties, the intent of the parties has to be

construed by reading the agreement as a whole in order to

determine whether it is an agreement simpliciter for

construction or an agreement that also creates an interest for

the builder in the property. Where under a development

agreement, the developer has an interest in land, it would be

difficult to hold that such an agreement is not capable of

being specifically enforced.”

(Italics and underscoring supplied)

22.7.2 Where, therefore, as in the present case, the agreement is not

merely for development or construction on the property, but also

envisages valuable rights enuring, in favour of the developer, in the

constructed edifice, the Supreme Court itself holds, unequivocally,

that it would be difficult to treat the agreement as incapable of specific performance.

22.8 The requirement of precision, in the construction contract, as a

pre-condition for its enforceability, is relatable to the erstwhile Section 14(3)(c)(iii) of the Specific Relief Act. That requirement no longer figures on the statute book, after the amendment of Section 14 by the 2018 Amendment Act. In my prima facie opinion, lack of precision in the construction agreement can no longer be regarded, by itself, as a sufficient disqualification to its enforceability by specific performance. Else, it would be re-introducing, by a side wind, the consideration in the erstwhile Section 14(3)(c)(iii), which the legislature has consciously removed from the statute. Such an

exercise is necessarily to be eschewed, as it would militate against the legislative intent.

22.9 The sequitur would, therefore, be that a construction contract

can no longer be regarded as incapable of specific performance merely because its terms are imprecise or vague. If, however, owing to such imprecision or vagueness, any direction for specific performance would require continuous supervision by the Court, that would, even now, render the agreement incapable of specific performance by virtue of Section 14(b). For that, however, the Court would have to arrive at a finding that, owing to the imprecision of the agreement, or for any other reason, any direction for specific performance would require continuous supervision by the Court. In the scenario of Section 14 as it exists today, and without the support of the erstwhile Section 14(3)(c) and its various clauses, this would, in almost every case, be arguable at the very least.

22.10 Prima facie, in view of the above legal position, I am unable to

convince myself to hold, prima facie, that the defendant has been able

to make out a case of the PDA being incapable of specific

performance, by operation of Section 14(b) of the Specific Relief Act,

as would justify vacation of the interim direction to maintain status

quo in respect of the suit property.

23. Re. Section 62 of the Contract Act and the plea of novation

23.1 Section 62 of the Contract Act, which accords statutory

recognition to the principle of novation of a contract, states that where

the parties to a contract consciously elect to substitute the existing

contract with another, the original contract need not be performed.

The submission of Mr. Garg is that the PDA stood novated by the

execution of the ATS, AFC and other agreements.

23.2 Prima facie, the plea of novation, as advanced by Mr. Garg is

completely misconceived on facts as well as in law. There is no

evidence of any inclination, much less indication, of the plaintiff and

defendant having agreed to substitute the PDA with any other

contract. This argument is, in fact, belied even by Clause 4 of the

PDA, which envisages the execution, at a later point of time, of the

ATS, AFC, GPA etc. The PDA and the documents to be executed

subsequently, form, therefore, a composite transaction. The

documents to be executed subsequently are intended to facilitate the

transfer of title and possession, as envisioned in the PDA. They owe

their existence, therefore, to the PDA. It would be militating against

the very intent of the PDA to hold that it stood novated with the

execution of the ATS, AFC etc.

23.3 On a holistic reading of the ATS and AFC, vis-à-vis the PDA, I

am unable to subscribe to the submission of Mr. Garg that there was

any such glaring inconsistency, between the documents, as would

evince an intent, on the part of the contracting parties, to do away with

the PDA and substitute the ATS, AFC and other documents in its

place.

23.4 On novation, the Supreme Court held, in Purbanchal Cables &

Conductors Pvt Ltd v. Assam State Electricity Board24, thus (in

para 82 of the report):

24 (2012) 7 SCC 462

“In our opinion the ground or issue of novation of contract is

a mixed question of fact and law and it is being raised for the

first time at the time of hearing of the case before us, which

cannot be permitted to be raised. The said fact of novation or

alteration of contract is required to be urged evidentially and

scrutinised by the courts below. In absence of such factual

findings, it is not possible to decide such a mixed question of

law and facts. In Shakti Tubes Ltd. v. State of Bihar,

(2009) 7 SCC 673 : (2009) 3 SCC (Civ) 258, the issue of

novation of contract was raised before this Court for the first

time at the time of hearing. This Court declined to entertain

such ground as being a mixed question of law and fact. This

Court further observed that even on the merits of the case the

escalation of price, reduction of the quantity of the supply

order and extension of the date of supply does not amount to

novation or alteration in the supply order.”

(Emphasis supplied)

Nearly a century and a quarter ago, one finds this clear exposition of

the principle of novation, in the judgement of the Court of the Judicial Commissioner at Nagpur in Ganpat v. Mahadeo  1925 Nag 26 :

“Where the question is whether one party is set free by the

action of the other, the matter for consideration is whether the

acts or conduct of the one do or do not amount to an

intimation of an intention to abandon and altogether to refuse

performance of the contract. The true question is whether the

acts and conduct of the party evince any intention no longer

to be bound by the contract: Mersay Steel and Iron

Company v. Naglir Benzon & Co. 9 A.C. 434 General Bill

Posting Co v. Atkinson (13). The Court requires as clear

evidence of the waiver as of the existence of the contract

itself and will not act upon less: Carolan v. Brabazon (1900)

A.C. 118 = 78 L.J.; C.H. 77=99 L.T. 913 = 25 T.L.R. 173.

What is then required is that an abandonment of the old

agreement, must be clearly made out. There must be clear

and precise evidence of a mutual intention to determine and

abandon the contract: Mathura Mohan Saha v. Ram

Kumar Saha [1946] 43 Cal. 700=23 C.L.J. 26 = 30 I.C.

305: 20 C.W.N. 370. Where the intention to substitute a new

contract is frustrated by the fact that the new contract is a

nullity, the original contract may be enforceable: see Har

Chandi Lal v. Sheoraj Singh 3 J & L 200 = 9 Ir. & E. 121.

Much more so, where the agreement itself is a contravention

of the statute and does not ripen into a contract in the legal

sense of the term.”

(Emphasis supplied)

A coordinate Bench of this Court has held, recently in Knowledge

Podium Systems Pvt Ltd v. S.M. Professional Services Pvt Ltd26,

that “a novation takes place only when there is a complete substitution of a new contract in place of the old”.

23.5 No such substitution of the PDA with the ATS, AFC and other

documents subsequently executed, in terms of Clause 4 of the PDA

itself, can, prima facie, be said to have taken place.

23.6 This argument of Mr. Garg, too, does not convince me to vary

the status quo order already passed.

24. Re. financial wherewithal of the plaintiff: Mr Garg has also

sought to plead that the plaintiff did not have the financial

wherewithal to comply with its obligation under the PDA. Mr

Wadhwa has disputed this contention, and has reiterated his client’s

willingness in this regard. At this stage, it is not possible for me, prima

facie, to hold that the plaintiff to be incapable of complying with its

obligations. The mere reference to the Axis Bank statement of the

plaintiff is hardly sufficient for the Court to be satisfied, even prima

facie, on this aspect. Of course, it would be for the defendant to

establish, during trial, its capability to adhere to its obligations under

26 278 (2021) DLT 348

the PDA.

Conclusion

25. As a result, I am of the opinion that the defendant has not been

able to make out any case to vacate the interim order passed by this

Court on 4th August, 2020.

26. Resultantly, I.A.7643/2020 is dismissed and the interim order

passed in I.A.6433/2020 is made absolute, pending disposal of the

suit. I.A. 6433/2020 stands allowed accordingly.

C. HARI SHANKAR, J.

OCTOBER 22, 2021


Print Page

No comments:

Post a Comment