Saturday, 11 September 2021

Whether arbitrator can grant increase in prices if there is delay in performance of contract due to fault of one party?

P.M. Paul v. Union of India [1989 Supp (1) SCC 368] is a case which is almost identical on facts. In this matter the work could not be completed during the period of the contract and the contractor was accordingly granted extension of time to complete the same. By an order of this Court, the dispute was referred to an arbitrator on the reference as to who was responsible for the delay in the completion of the work, what were to be the repercussions of the delay and how to apportion the responsibility and the consequences. The arbitrator made an award in favour of the contractor which was duly challenged by the Union of India with the matter finally reaching this Court at the instance of the contractor and this is what the Court had to say : (SCC p. 373, para 13)

13. It was submitted that if the contract work was not completed within the stipulated time which it appears was not done then the contractor has got a right to ask for extension of time, and he could claim difference in price. This is precisely what he has done and has obtained a portion of the claim in the award. It was submitted on behalf of the Union of India that failure to complete the contract was not the case. Hence, there was no substance in the objections raised. Furthermore, in the objections raised, it must be within the time provided for the application under Section 30 i.e. 30 days during which the objection was not specifically taken, we are of the opinion that there is no substance in this objection sought to be raised in opposition to the award. Once it was found that the arbitrator had jurisdiction to find that there was delay in execution of the contract due to the conduct of the respondent, the respondent was liable for the consequences of the delay, namely, increase in prices. Therefore, the arbitrator had jurisdiction to go into this question. He has gone into that question and has awarded as he did.”{Para 19}

IN THE SUPREME COURT OF INDIA

Civil Appeal Nos. 3376-3337 of 2008

Decided On: 07.05.2008

Associated Construction  Vs. Pawanhans Helicopters Pvt. Ltd.

Hon'ble Judges/Coram:

Tarun Chatterjee and H.S. Bedi, JJ.


Author: H.S. Bedi, J.

Citation: AIR2008SC 2911, 2008(2)ARBLR473(SC ), 2008 (3) AWC 3048 (SC ), 2008-4-LW926, 2009(1)RC R(C ivil)34,

2008(8)SC ALE451, (2008)16SC C 128,MANU/SC/7630/2008

1. Leave granted.

2. The respondent, Pawanhans Helicopters Pvt. Ltd. (hereinafter called "Pawanhans")

a Government of India undertaking, floated two tenders for allocation of work for

construction of a compound wall and a bridge over a nala. Pursuant to the aforesaid

information, several tenders were received and the tenders of the appellant

(hereinafter called the "contractor") were ultimately accepted. Pursuant to the

aforesaid, two formal agreements providing for the terms and conditions of the

09-09-2021 

contract in the shape of general conditions of the contract and special conditions of

the contract governing the execution of work were duly signed on 12th October 1999.

As per the contract the work was required to be completed within four months. It

appears that on account of some delay which was attributable to Pawanhans, the

work did not proceed as per schedule and the contractor accordingly informed

Pawanhans by letters dated 15th February 1990, 23rd February 1990, 24th March

1990, 26th June 1990 and 6th July 1990 that the work was getting delayed as the

requisite facilities for its completion had not been provided and highlighting several

factors attributable to it had supervened which had led to the delay. The contractor

also in the meanwhile vide letters dated 27th July 1990 and 6th August 1990

requested the respondent to release the outstanding bills against the work already

completed and also requested for the "Virtual Completion Certificate" vide letter dated

25th August 1990. As some work on the compound wall still remained to be

completed, the contractor agreed to take up this assignment subject to waiver of the

discount of 8.2% which was to be given to Pawanhans till then and the completed

works were duly handed over to Pawanhans on the 12th November 1990. The

contractor had also submitted a bill dated 23rd June 1991 and it was conveyed to

Pawanhans that it expected compensation on account of the variation in the terms of

the contract. Pawanhans thereupon advised the contractor to submit a final bill which

too was submitted. The bill was verified by Pawanhans and referred to the contractor

yet again with objections. The contractor vide letter dated 21st November 1991

disputed the verification as being without any foundation and also reserved its right

to seek arbitration. After a protracted correspondence, Pawanhans vide letter of 9th

December 1991 advised the contractor to submit a "No Claim Certificate" as a precondition

for the release of the balance payment. The contractor wrote to Pawanhans

that it was in dire need of finances and was being subjected to duress but

nevertheless submitted a "No Dues Certificate" dated 17th February 1992 once again

specifically highlighting that the same was being issued under duress. It appears that

despite the issuance of the aforesaid certificate, Pawanhans still did not release the

payment on which the contractor wrote another letter dated 5th May 1992 and several

letters thereafter but again to no effect, and on the contrary received a letter dated

8th June 1992 from Pawanhans asking for a "No Dues Certificate" as per the enclosed

specimen without attaching any condition to the same. The contractor, now in a

desperate situation, submitted yet another "No Claim Certificate" dated 18th June

1992 as per directions. After receiving the aforesaid document, Pawanhans in its

letter dated 9th February 1993 informed the contractor that a period of two months

would be required for the scrutiny of its bills and vide letter dated 21st May 1993

also intimated that the bills had been submitted for verification by the

Architect/Engineer as per the terms of the contract and that in case it was willing to

defray the payment, the matter could be referred to arbitration. The contractor finally

received a communication dated 8th June 1993 pointing out that as all payments due

under the contract had been made and as a "No Dues Certificate" had been furnished,

no further amount was due. The contractor accordingly served a notice dated 28th

June 1993 on Pawanhans invoking the clause relating to arbitration. The matter was

referred to arbitration by two registered Architects as per the clause. The contractor

submitted its statement of claim for the outstanding amount plus compensation and

damages on 6th August 1994. The arbitrators passed two awards on 31st December

1996, one with respect to the contract for the compound wall and the second for the

construction of the bridge awarding certain amounts to the contractor. Aggrieved by


the awards, Pawanhans filed two separate petitions under Sections 30 and 33 of the

Arbitration Act, 1940 before the Bombay High Court for a direction that the awards be

set aside. The learned Single Judge in his judgment and order dated 9th December

1998 held that Clauses 18 and 34 of the contract when read together, provided for

the payment of escalation charges as the work had not been completed within four

months on account of the fault on the part of the respondent and that the said

clauses did not prohibit such a payment, more particularly as time was the essence of

the contract and as the contract was not on a fixed price, the prohibition of escalation

was if at all to be read during the period of contract only. The learned Single Judge

also repelled the arguments of the respondent that after having submitted the final

bill on 25th October 1991, it was not open to the appellant herein to submit a second

final bill on 2nd February 1993 by observing that the payment received on the 4th

July 1993 as a consequence of the bills submitted on 25th October 1991, was under

duress and it is on that account that the appellant had given the aforesaid certificate.

Some objections raised by the respondent herein were however accepted by the

learned Single Judge and the award was accordingly modified and it is the admitted

case that the aforesaid modification has been accepted and was not challenged before

the Division Bench by the contractor.

3. Two appeals were thereafter filed by Pawanhans before the Division Bench of the

Bombay High Court. The Division Bench vide its order dated 7th June 2007 allowed

the appeals and set aside the order dated 9th December 1998 of the learned Single

Judge as also the two awards dated 31st December 1996 by highlighting as a preface

that it could not be disputed that the scope for interference by the court under

Section 30 or 33 of the Arbitration Act was limited as the court could not sit as a

court of appeal on the decisions arrived at by the arbitrator. The Court then applied

the aforesaid principle to the facts of the case and relied on Clauses 18 and 34 ibid

observed that a plain reading of the said clauses did not visualize any claim for

escalation or reduction towards the cost of the work and again reiterated that Clause

34 of the agreement prohibited the contractor from claiming any extra amount on

account of fluctuation of price. The Court further observed, somewhat in

contradiction, that a remedy towards the escalation of price had been provided by

Clause 43 of the contract and Clause 43-1(E) specifically provided, the procedure

whereby such a claim could be made and as the procedure prescribed by the clause

had not been adopted, it was not open to the contractor to contend before the

arbitrator that it was entitled to some payments on account of price escalation. The

Court finally concluded that:

Once it is clear that the respondents are not entitled to claim escalation

charges and the entire dispute, which is the subject matter of the appeals

being related to the escalation charges, the impugned orders, to the extent

they confirm the award in relation to the escalation charges, are liable to be

set aside and the petitions filed by the appellants challenging the awards in

relation to the grant of the escalation charges are liable to be allowed to that

extent. Consequently, the claims for interest on the amount of damages

awarded towards the escalation are also liable to be set aside.

4 . The Division Bench then examined the issues raised by the contractor as to

whether that "No Due Certificate" had been given under duress and held that there

was no evidence to show that the said certificate had been given under duress or

coercion and as the certificate itself provided a clearance of no dues, the contractor

could not now turn and say that any further payment was still due on account of the


second final bill. The Division Bench accordingly allowed the appeal. The matter is

before us in these circumstances.

5. Mr. Shyam Divan, the learned senior counsel for the contractor, has raised several

arguments before us during the course of the hearing. He has first pointed out that

the awards rendered by the arbitrator were non-speaking and in this view of the

matter, the scope for judicial interference was extremely limited and interference with

the findings of the Arbitrators was, therefore, not called for. He has also pleaded that

Clauses 18 and 34, as per their plain interpretation themselves visualized a claim for

escalation where the delay had been caused by the opposite party and that in any

case, the bar on the escalation, if at all, could be restricted only for the period of

contract i.e. four months and not thereafter. He has also submitted that Clause 43-

1(C) on which reliance had been placed by the Division Bench for non-suiting the

contractor, was misplaced as this clause too did not specifically or even by

implication whittle down the effects of Clauses 18 and 34. It has also been argued

that the finding of the Division Bench that there was no duress on the contractor

relating to the issuance of the "No Claim Certificates" was incorrect in the light of the

voluminous evidence to the contrary on record.

6. Mr. Raju Ramachandran, the learned senior counsel appearing for Pawanhans has

fairly and at the very outset pointed out that the award in question was non-speaking

and as such the scope for interference by the court was limited. He has further

contended that it would perhaps be difficult to read into the clauses a complete bar

towards escalation, as a court would be reluctant to visualize such a bar in the light

of some unforeseen situations that might arise in the execution of a work and the

gates, thus, could not for ever be closed, but has submitted that Clause 43 provided

for such an opening and as this procedure had not been adopted by the contractor,

the claim under Clauses 18 and 34 was not maintainable. He has also submitted that

the "No Dues Certificate" having once being given by the contractor, it was not open

to it to make a volte-face and to challenge the said certificate on the ground that it

had been given under duress and the finding of the Division Bench on this point was,

therefore, correct.

7 . We have heard the learned Counsel for the parties and gone through the record.

As would be apparent, the matter would rest on an interpretation of Clauses 34, 43

(1) and (2) of the General Conditions of the Contract and Clause 18 of the Special

Conditions of the Contract. We reproduce herein below the clauses abovementioned:

34. The contractor shall not claim any extras for fluctuation of price and the

contract price shall not be subject to any rise or fall of prices.

43 (1) E. Architect's instructions issued in regard to the postponement of any

work to be executed under the provisions of this contract; and if the written

application is made within a reasonable time of it becoming apparent that the

progress of the work or of any part thereof has been affected as aforesaid:

Then the Architect shall ascertain the amount of such loss and/or

expense. Any amount from time to time so ascertained shall be

added to the amount which would otherwise be stated as due in such

certificate.

43 (2) The provisions of this condemn are without prejudice to any

other rights and remedies which the contractor may possess.


18. It is specifically pointed out that the contractor shall not be entitled to

any compensation whatsoever on account of:

1. Any delay in supply of any material.

2. Any increase in costs of any material.

3. Any subsequent increase in cost of any material due to increase in

other charges like Railway, Steamer, freights or taxes and duties.

4. Any increase in labour costs.

8. We have examined the arguments raised by the learned Counsel in the light of the

aforesaid and other provisions. It is the admitted position that as per Clause 38, the

date of the commencement of the contract was 1st November. 1989 and the date

stipulated for the completion of the work was 28th February 1990. It is also clear

from Sub-clause (7) of Clause 1 of the General Conditions that time would be the

essence of the contract. We also see from Clause 43 aforequoted that this clause has

within itself the clear indication that the embargo placed by Clauses 18 and 34 was

not sacrosanct as has been found by the Division Bench as there could be a situation

where the contractor had suffered loss for whatever reasons which was required to be

reimbursed as per procedure prescribed in Clause 43. Clause 43 (2) also specifically

provided that Clause 43 was without prejudice to any other rights and remedies that

the contractor might possess. We find from a reading of the judgment of the Division

Bench that the contractor has been non-suited on the plea that it had failed to

proceed under Clause 43. On the contrary we believe that Clause 43 is a clause which

should be read in aid of the contractor as it clearly provides for indemnity in case

there was a delay in the completion of the work which could be attributable to

Pawanhans. We are, further, of the opinion that even assuming for a moment that

there could be no price escalation during the period of 4 months i.e. during the

pendency of the contract, such embargo would not be carried beyond that period as

time was the essence of the contract. The learned Division Bench has relied upon a

large number of judgments in support of its decision that in case of a clause barring

the escalation in the price, it was not open to the contractor to claim any amount

under that head. A perusal of the aforesaid judgments, however, do not show any

provision in terms of Clause 43, and that in any case, these judgments pertain to a

claim of price escalation during the period of contract. It must also be borne in mind

that a court does not sit as one in appeal over the award of the arbitrator and if the

view taken by the arbitrator is permissible, no interference is called for on the

premise that a different view was also possible. We also feel that in commercial

transactions all situations cannot be visualized and the positive and unchallenged

finding in the present case is that the delay in the execution of the work was

occasioned on account of reasons attributable to Pawanhans. It cannot, therefore, be

said that the award of the arbitrator was so unconscionable that it required

interference. In MCD v. Jagan Nath Ashok Kumar and Anr. MANU/SC/0013/1987

: [1988]1SCR180 , it was observed thus:

In this case, there was no violation of any principles of natural justice. It is

not a case where the arbitrator has refused cogent and material factors to be

taken into consideration. The award cannot be said to be vitiated by nonreception

of material or non- consideration of the relevant aspects of the

matter. Appraisement of evidence by the arbitrator is ordinarily never a

matter which the court questions and considers. The parties have selected


their own forum and the deciding forum must be conceded the power of

appraisement of the evidence. In the instant case, there was no evidence of

violation of any principle of natural justice. The arbitrator in our opinion is

the sole judge of the quality as well as quantity of evidence and it will not be

for this Court to take upon itself the task of being a judge of the evidence

before the arbitrator. It may be possible that on the same evidence the court

might have arrived at a different conclusion than the one arrived at by the

arbitrator but that by itself is no ground in our view for setting aside the

award of an arbitrator.

and further concluded:

After all an arbitrator as a judge in the words of Benjamin N. Cardozo, has to

exercise a discretion informed by tradition, methodized by analogy,

disciplined by system, and subordinated to "the primordial necessity of order

in the social life.

9 . P.M. Paul v. Union of India MANU/SC/0399/1989) is a case which is almost

identical on facts. In this matter the work could not be completed during the period

of the contract and the contractor was accordingly granted extension of time to

complete the same. By an order of this Court, the dispute was referred to an

Arbitrator on the reference as to who was responsible for the delay in the completion

of the work, what were to be the repercussions of the delay and how to apportion the

responsibility and the consequences. The arbitrator made an award in favour of the

contractor which was duly challenged by the Union of India with the matter finally

reaching this Court at the instance of the contractor and this is what the Court had to

say.

It was submitted that if the contract work was not completed within the

stipulated time which it appears was not done then the contractor has got a

right to ask for extension of time, and he could claim difference in price. This

is precisely what he has done and has obtained a portion of the claim in the

award. It was submitted on behalf of the Union of India that failure to

complete the contract was not the case. Hence, there was no substance in the

objections raised. Furthermore, in the objections raised, it must be within the

time provided for the application under Section 30 i.e., 30 days during which

the objection was not specifically taken, we are of the opinion that there is

no substance in this objection sought to be raised in opposition to the award.

Once it was found that the arbitrator had jurisdiction to find that there was

delay in execution of the contract due to the conduct of the respondent, the

respondent was liable for the consequences of the delay, namely, increase in

prices. Therefore, the arbitrator had jurisdiction to go into this question. He

has gone into that question and has awarded as he did.

10. A similar view has been taken by this Court in K.N. Sathyapalan (D) By Lrs. v.

State of Kerala and Anr. MANU/SC/5270/2006 : 2006(12)SCALE654 . It has been

held as under:

We have intentionally set out the background in which the Arbitrator made

his award in order to examine the genuineness and/or validity of the

appellant's claim under those heads which had been allowed by the

Arbitrator. It is quite apparent that the appellant was prevented by

unforeseen circumstances from completing the work within the stipulated


period of eleven month and that such delay could have been prevented had

the State Government stepped in to maintain the law and order problem

which had been created at the work site. It is also clear that the rubble and

metal, which would have been available at the departmental quarry at

Mannady, had to be obtained from quarries which were situated at double the

distance, and even more, resulting in doubling of the transportation charges.

Even the space for dumping of excess earth was not provided by the

respondents which compelled the appellant to dump the excess earth at a

place which was for away from the work site entailing extra costs for the

same.

In the aforesaid circumstances, the Arbitrator appears to have acted within

his jurisdiction in allowing some of the claims on account of escalation of

costs which was referable to the execution of the work during the extended

period, In our judgment, the view taken by the High Court was on a rigid

interpretation of the terms of contract and the Supplemental Agreement

executed between the parties, which was not warranted by the turn of events.

11. We are, therefore, of the opinion in the light of the aforesaid judgments, that it

was open to the contractor to contend that it was liable to be compensated on

account of the fact that delay had been occasioned on account of reasons attributable

to Pawanhans. It is significant that the Division Bench of the High Court has been

silent on this aspect of the matter and has not referred to the finding of the learned

Single Judge with regard to the responsibility for the delay.

1 2 . We are further of the opinion that Clause 43 and 43 (1) and (2) when read

together clearly visualize escalation of price on account of reasons beyond the control

of the contractor and attributable to the other side. Moreover Clause 43 (2) clearly

states that the remedy under Clause 43(1) would be in addition to such other remedy

that may be open to the contractor under the other provisions.

13. We have also gone through the record with respect to the finding of the Division

Bench that there was no duress or coercion on the contractor which had compelled it

to give a "No Dues Certificate". Mr. Raju Ramachandran has, however, submitted that

the story about duress was an after thought in the background that the first final bill

had been submitted by the contractor on the 3rd June 1991 and the second final bill

on 2nd February 1993 i.e. almost 2 years later and that in any case, a second final bill

was not visualized under the contract. He has submitted that the observation of the

arbitrator that submission of the second final bill was sanctioned as a trade practice

was without any basis. We have gone through the record in the light of the

submissions of the learned Counsel. We first refer to the letter of the contractor of

11th July 1990 to which reference has been made by the Division Bench requesting

Pawanhans to ensure a regular power supply. The letter of 27th July 1990 by the

contractor refers to the statement of accounts submitted by it and requests for

payment as per the accounts which had been cleared by the Architect. It is to be

noted that these letters are on the record and were written by the contractor at the

time when the work was in the process of completion. The desperate tone of the

contractor is however supported by the letter of 10th January 1991 in which it was

noted that though repeated requests had been made for the payment atleast against

the bills certified by the Architect, a huge amount had been blocked arbitrarily over a

long period of time and a request was made for its release. The letter dated 21st

November 1991 is again a reminder to Pawanhans asking for payment and that in


case there was a dispute, the matter be referred to the arbitrator and submitting that

payment should be made atleast with respect to those dues which had been certified

by the Architect. The letter dated 9th December 1991 from Pawanhans to the

contractor shows that payment could be considered provided the contractor submitted

a "No Claim Certificate". It appears that such certificate was indeed issued but with

no result on which the contractor in his letter dated 26th December 1991 in reply to

the letter dated 9th December 1991, once again submitted that the payments be

released in so far as they had been certified by the Architects/Consultants and if there

was a dispute regarding the other payments, they should be referred to an arbitrator

and in desperation further adds:

However, if you want to hold us to economic duress by not paying what you

wish to pay, without "No Claim Certificate", we shall treat it as "Duress" and

issue you such a certificate much against our willingness as we cannot afford

to liquidate our dues by such a certificate.

Please do not hold us to a ransom and arrange to pay. In case you would still

like to insist, let us know, so that we could issue you such a certificate under

duress as we have serious financial problems.

14. It appears that despite the pleading tone of the aforesaid letter no payment was

made on which the contractor wrote yet another letter dated 17th February 1992 in

which it was submitted as under:

Inspite of our claim statements, you have insisted on "No Claim Certificate",

we hereby give you this certificate that we have "No Claims" and hence you

pay us what you might have worked out as our "Final Dues".

In case, you have a particular draft in which a "No Claim" Certificate need be

issued to receive our dues of our bill, please let us have the deft, or else this

letter may be treated as the certificate of "No Claim" from our side.

15. When no action was taken, another letter dated 5th May 1992 was addressed to

Pawanhans by the contractor stating that as they were facing economic duress on

account of the payment being held back, and as a "No Claim Certificate" had been

issued, the payment be defrayed as promised or else they might have to refer the

matter to the arbitrator. The letter dated 8th June 1992 is again tell-tale and we

reproduce the contents hereunder:

Kindly let us know what is it that we have to do to get money which you say

is payable but only on your extracting "No Claim" certificate under duress.

Please take note if you fail to pay us our dues, we shall be constrained to

take you to court for which you will blame yourself if it inconvenience is

caused. It is a clear 15 days notice please.

16. It appears however that no steps were taken on which the contractor addressed a

letter dated 2nd February 1993 for payment of dues and again stated that if the

payment was not made, the dispute should be referred to the arbitrator. In response

to this letter, Pawanhans in its letter dated 9 th February 1993 replied that the matter

was under scrutiny and it would take about 2 months for verification and that the

contractor would be informed in due course. As no reply was received, a letter dated

21st May 1993 was addressed by the contractor relating to the undertaking that the


enquiry would be completed within 2 months but complaining that nothing had been

done and on the contrary on 8th June 1993 the claim for any payment was rejected

by Pawanhans observing that as a "No Dues Certificate" had been submitted by the

contractor, the question of any balance payment being due did not arise. It is at this

stage that the contractor had invoked the clause for arbitration. We have reproduced

the correspondence in extenso to show that the contractor was compelled to issue a

"No Dues Certificate" and in this view of the matter, it could not be said that the

contractor was bound by what he had written. It is also clear that there is voluminous

correspondence over a span of almost 2 years between the submission of the first

final bill on 3rd June 1991 and the second final bill dated 2nd February 1993 and as

such the claim towards escalation or the plea of the submission of a "No Dues

Certificate" under duress being an after thought is not acceptable. In Ambica

Construction v. Union of India MANU/SC/5180/2006 : 2006(12)SCALE149 it was

observed as under:

A glance at the said clause will immediately indicate that a No Claim

Certificate is required to be submitted by a contractor once the works are

finally measured up. In the instant case the work was yet to be completed

and there is nothing to indicate that the works, as undertaken by the

contractor, had been finally measured and on the basis of the same a No

Objection Certificate had been issued by the appellant. On the other hand,

even the first Arbitrator, who had been appointed, had come to a finding that

No Claim Certificate had been given under coercion and duress. It is the

Division Bench of the Calcutta High Court which, for the first time, came to a

conclusion that such No Claim Certificate had not been submitted under

coercion and duress.

From the submissions made on behalf of the respective parties, and in

particular from the submissions made on behalf of the appellant, it is

apparent that unless a discharge certificate is given in advance, payment of

bills are generally delayed. Although, Clause 43(2) has been included in the

General Conditions of Contract, the same is meant to be a safeguard as

against frivolous claims after final measurement. Having regard to the

decision in the case of Reshmi Constructions's (supra), it can no longer be

said that such a clause in the contract would be an absolute bar to a

contractor raising claims which are genuine, even after the submission of

such No Claim Certificate.

1 7 . We are therefore of the opinion that the judgment of the Division Bench is

erroneous and we accordingly set it aside. The judgment of the learned Single Judge

is accordingly restored. In the facts and circumstances of the case, in that Pawanhans

has taken advantage of a beleaguered contractor, and has behaved in a most

unbecoming manner in pushing it ever deeper into the chasm, the contractor will

have its costs which are computed at Rs. 10,000/-. The appeals are accordingly

allowed.


Print Page

No comments:

Post a Comment