In the decision reported in Kalpakam Amma Vs.
Muthurama Iyer [1994 (2) KLT 424], it has been
held that when there is a lease of a building, such lease
would normally take in the site unless it is specifically
excluded. It is also stated in the decision that
destruction of the building does not automatically
terminate the lease and put an end to landlord-tenant
relationship. Since there were conflicting decisions on
the question as to whether on the destruction of the
subject matter of the lease, whether the lease will come
to end, it was referred to a larger Bench of the Apex
Court and the Three Judges Bench of the Apex Court in
Shaha Ratansi Khimji Vs. Proposed Kumbhar Sons
Hotel Pvt.Ltd. [2014 (3)KLT 1014 (SC)] held that
once the right of lease is transferred in favour of the
lessee, the destruction of a building constructed on the
lease property does not determine the tenancy rights of
occupant which is incidental to the contract of lease
which continues to exist between them.
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
MR. JUSTICE K.RAMAKRISHNAN
1ST DAYOF AUGUST 2016.
CRP.No. 139 of 2016
MOHANDAS K.B.,
SYAMALA,
Citation: AIR 2017 (NOC)1 Ker
1.The above revision has been filed against the order,
dismissing E.P.No.23/2015 in O.S.No.159/1994 on the
file of the Munisff Court, Mannarkkad. The suit was filed
by the predecessor of the revision petitioners as
O.S.No.159/1994 for recovery of possession of the
building which was let out to the predecessor of the
respondents. The building is situated in an area where
the provisions of Rent Control Act is not extended. The
suit was decreed as per Annexure A-1 Decree and it was
confirmed in A.S.No.24/2002 on the file of the Sub
Court, Ottapalam. The original plaintiff died during the
pendency of the appeal and the present petitioners have
been impleaded as additional respondents in the appeal
as his legal heirs and the appeal was also dismissed.
The present petitioners filed E.P.No.23/2015 for
executing the decree which was dismissed by the court
below on the ground that the subject matter of the suit
is destroyed and delivery could not be effected. This is
being challenged by the revision petitioners before this
Court.
2.Though notice was served on the respondents, they did
not appear.
3.Heard Shri.C.P.Peethambaran, the learned counsel for
the revision petitioners.
4. The counsel for the revision petitioners submitted that
the dismissal of the Execution Petition as not executable
due to destruction of the building is unsustainable in
law as the court below ought to have delivered the
property in which the building existed. He had relied on
the decisions reported in Kandaru Veettil
Ramakrishnan's Son Preman Vs. Kadaruveettil
Ramakrishnan's Son Gopi [ILR 2016 (1) KER 746],
Shaha Ratansi Khimji Vs. Proposed Kumbhar Sons
Hotel Pvt. Ltd.[2014 (3) KLT 1014 (SC)] and
Kalpakam Amma Vs. Muthurama Iyer [1994 (2)
KLT 424].
5.The fact that the suit was filed by the predecessor of
the revision petitioners for eviction of the building from
the possession of the predecessor of the respondents as
O.S.No.159/1994 on the file of the Munsiff Court,
Mannarkad and that was decreed and appeal filed
against the same was also dismissed, is not in dispute.
It is also an admitted fact that the revision petitioners
filed E.P.No.23/2015 for execution of the decree, as the
original plaintiff died during the pendency of the appeal
and the present revision petitioners have been
impleaded as his legal heirs in that appeal.
6.The court below dismissed the Execution Petition by the
impugned order which reads as follows:
"Heard. As per the decree, the plaint schedule
property was ordered to be evicted Plaint schedule
property is the building premise. Amin reported
that the building shown in the decree schedule is
not in existence and not seen. Since the subject
matter of the suit is destroyed, E.P. is dismissed."
7. In the decision reported in Kalpakam Amma Vs.
Muthurama Iyer [1994 (2) KLT 424], it has been
held that when there is a lease of a building, such lease
would normally take in the site unless it is specifically
excluded. It is also stated in the decision that
destruction of the building does not automatically
terminate the lease and put an end to landlord-tenant
relationship. Since there were conflicting decisions on
the question as to whether on the destruction of the
subject matter of the lease, whether the lease will come
to end, it was referred to a larger Bench of the Apex
Court and the Three Judges Bench of the Apex Court in
Shaha Ratansi Khimji Vs. Proposed Kumbhar Sons
Hotel Pvt.Ltd. [2014 (3)KLT 1014 (SC)] held that
once the right of lease is transferred in favour of the
lessee, the destruction of a building constructed on the
lease property does not determine the tenancy rights of
occupant which is incidental to the contract of lease
which continues to exist between them. The Supreme
Court has over ruled the decision reported in
Vannattankandy Ibrayi Vs. Kunhabdulla Hajee
[2001 (1) SCC 564] and approved the dictum laid
down in the decision reported in T. Lakshmipathi and
Others Vs. P.Nithyananda Reddy and Others [2003
(5) SCC 150], where it has been held that the lease of
the building includes the land on which the building
stands. So, even if the building is destroyed or
demolished, the lease is not determined as long as the
land beneath it continues to exist. The doctrine of
frustration cannot be invoked on destruction or
demolition of building under lease where not only privity
of contract, but, privity of estate is also created. In the
same decision, it has been held that, unless the lease
has been terminated, merely because the structure has
been destroyed will not terminate the lease entitled to
the landlord to take possession without recourse to law.
So, the tenancy will have to be terminated and in such
cases, the landlord is entitled to file a civil suit for
recovery of possession. The same view has been
reiterated in the latest decision reported in Preman Vs.
Gopi [I.L.R. 2016 (1) Kerala 746]. So, merely
because the subject matter of the suit (namely, the
building) has been destroyed is not a ground for
dismissing the Execution Petition. In this case, instead
of the Rent Control Petition, the suit has been filed by
the landlord after terminating the lease by issuing
notice under Section 106 of Transfer of Property Act.
So, in such cases, in view of the principles laid down in
the above decisions, even if the building is destroyed,
the landlord is entitled to recover the land in which the
building existed. So, the court below was not justified
in dismissing the application on the ground of
destruction of the building which is the subject matter
of the lease. The court below ought to have identified
the property in which the building existed and effected
delivery of the same to the decree holder. So, the
order dismissing the Execution Petition is set aside and
the matter is remitted to the court below for fresh
disposal in accordance with law as stated above.
Sd/-
K.Ramakrishnan,
Judge.
Muthurama Iyer [1994 (2) KLT 424], it has been
held that when there is a lease of a building, such lease
would normally take in the site unless it is specifically
excluded. It is also stated in the decision that
destruction of the building does not automatically
terminate the lease and put an end to landlord-tenant
relationship. Since there were conflicting decisions on
the question as to whether on the destruction of the
subject matter of the lease, whether the lease will come
to end, it was referred to a larger Bench of the Apex
Court and the Three Judges Bench of the Apex Court in
Shaha Ratansi Khimji Vs. Proposed Kumbhar Sons
Hotel Pvt.Ltd. [2014 (3)KLT 1014 (SC)] held that
once the right of lease is transferred in favour of the
lessee, the destruction of a building constructed on the
lease property does not determine the tenancy rights of
occupant which is incidental to the contract of lease
which continues to exist between them.
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT:
MR. JUSTICE K.RAMAKRISHNAN
1ST DAYOF AUGUST 2016.
CRP.No. 139 of 2016
MOHANDAS K.B.,
SYAMALA,
Citation: AIR 2017 (NOC)1 Ker
1.The above revision has been filed against the order,
dismissing E.P.No.23/2015 in O.S.No.159/1994 on the
file of the Munisff Court, Mannarkkad. The suit was filed
by the predecessor of the revision petitioners as
O.S.No.159/1994 for recovery of possession of the
building which was let out to the predecessor of the
respondents. The building is situated in an area where
the provisions of Rent Control Act is not extended. The
suit was decreed as per Annexure A-1 Decree and it was
confirmed in A.S.No.24/2002 on the file of the Sub
Court, Ottapalam. The original plaintiff died during the
pendency of the appeal and the present petitioners have
been impleaded as additional respondents in the appeal
as his legal heirs and the appeal was also dismissed.
The present petitioners filed E.P.No.23/2015 for
executing the decree which was dismissed by the court
below on the ground that the subject matter of the suit
is destroyed and delivery could not be effected. This is
being challenged by the revision petitioners before this
Court.
2.Though notice was served on the respondents, they did
not appear.
3.Heard Shri.C.P.Peethambaran, the learned counsel for
the revision petitioners.
4. The counsel for the revision petitioners submitted that
the dismissal of the Execution Petition as not executable
due to destruction of the building is unsustainable in
law as the court below ought to have delivered the
property in which the building existed. He had relied on
the decisions reported in Kandaru Veettil
Ramakrishnan's Son Preman Vs. Kadaruveettil
Ramakrishnan's Son Gopi [ILR 2016 (1) KER 746],
Shaha Ratansi Khimji Vs. Proposed Kumbhar Sons
Hotel Pvt. Ltd.[2014 (3) KLT 1014 (SC)] and
Kalpakam Amma Vs. Muthurama Iyer [1994 (2)
KLT 424].
5.The fact that the suit was filed by the predecessor of
the revision petitioners for eviction of the building from
the possession of the predecessor of the respondents as
O.S.No.159/1994 on the file of the Munsiff Court,
Mannarkad and that was decreed and appeal filed
against the same was also dismissed, is not in dispute.
It is also an admitted fact that the revision petitioners
filed E.P.No.23/2015 for execution of the decree, as the
original plaintiff died during the pendency of the appeal
and the present revision petitioners have been
impleaded as his legal heirs in that appeal.
6.The court below dismissed the Execution Petition by the
impugned order which reads as follows:
"Heard. As per the decree, the plaint schedule
property was ordered to be evicted Plaint schedule
property is the building premise. Amin reported
that the building shown in the decree schedule is
not in existence and not seen. Since the subject
matter of the suit is destroyed, E.P. is dismissed."
7. In the decision reported in Kalpakam Amma Vs.
Muthurama Iyer [1994 (2) KLT 424], it has been
held that when there is a lease of a building, such lease
would normally take in the site unless it is specifically
excluded. It is also stated in the decision that
destruction of the building does not automatically
terminate the lease and put an end to landlord-tenant
relationship. Since there were conflicting decisions on
the question as to whether on the destruction of the
subject matter of the lease, whether the lease will come
to end, it was referred to a larger Bench of the Apex
Court and the Three Judges Bench of the Apex Court in
Shaha Ratansi Khimji Vs. Proposed Kumbhar Sons
Hotel Pvt.Ltd. [2014 (3)KLT 1014 (SC)] held that
once the right of lease is transferred in favour of the
lessee, the destruction of a building constructed on the
lease property does not determine the tenancy rights of
occupant which is incidental to the contract of lease
which continues to exist between them. The Supreme
Court has over ruled the decision reported in
Vannattankandy Ibrayi Vs. Kunhabdulla Hajee
[2001 (1) SCC 564] and approved the dictum laid
down in the decision reported in T. Lakshmipathi and
Others Vs. P.Nithyananda Reddy and Others [2003
(5) SCC 150], where it has been held that the lease of
the building includes the land on which the building
stands. So, even if the building is destroyed or
demolished, the lease is not determined as long as the
land beneath it continues to exist. The doctrine of
frustration cannot be invoked on destruction or
demolition of building under lease where not only privity
of contract, but, privity of estate is also created. In the
same decision, it has been held that, unless the lease
has been terminated, merely because the structure has
been destroyed will not terminate the lease entitled to
the landlord to take possession without recourse to law.
So, the tenancy will have to be terminated and in such
cases, the landlord is entitled to file a civil suit for
recovery of possession. The same view has been
reiterated in the latest decision reported in Preman Vs.
Gopi [I.L.R. 2016 (1) Kerala 746]. So, merely
because the subject matter of the suit (namely, the
building) has been destroyed is not a ground for
dismissing the Execution Petition. In this case, instead
of the Rent Control Petition, the suit has been filed by
the landlord after terminating the lease by issuing
notice under Section 106 of Transfer of Property Act.
So, in such cases, in view of the principles laid down in
the above decisions, even if the building is destroyed,
the landlord is entitled to recover the land in which the
building existed. So, the court below was not justified
in dismissing the application on the ground of
destruction of the building which is the subject matter
of the lease. The court below ought to have identified
the property in which the building existed and effected
delivery of the same to the decree holder. So, the
order dismissing the Execution Petition is set aside and
the matter is remitted to the court below for fresh
disposal in accordance with law as stated above.
Sd/-
K.Ramakrishnan,
Judge.
No comments:
Post a Comment