Sunday, 22 June 2014

Construction of court building Vs interest of private party



  The trial court has rightly observed that if there is no 
document   which   show   that   the   suit   property   has   been 
earmarked as separate land for N.A.use, then, the acquisition 
record cannot be brushed aside.  The award is made by the very 
same revenue officer in his capacity as Special Land Acquisition 
Officer.   He  had before him all the maps, measurements and 
records   and   it   is   only   then,   he   considered   the   claim   of   the 
appellants   for   compensation.     In   these   circumstances,   to 
displace and  dislodge the statements made in the award and 
which is of 18th  April 1992 at this prima facie state would be 
improper.  The learned Judge has referred to each of the maps 
and it is erroneous on the part of the appellants to urge that 

they have been brushed aside.  The learned Judge has referred 
to them and equally to the further steps taken culminating in 
the order dated 24th  February 2012.   It is after considering all 
these   materials,   that   he   arrived   at   a   conclusion   that   the 
appellants   –   plaintiffs   have   failed   to   make   out   a   prima   facie 
case.  The Balance of convenience is also not in their favour and 

they will not suffer grave or irreparable loss, harm and injury 
but construction of the court building is a public project and if it 
is stopped at this stage, that would be not in public interest. 
The overwhelming public interest  is paramount in such cases 
whereas   if   the   appellants   ultimately   succeed,   they   can   be 
compensated in terms of money or with appropriate direction.



APPEAL FROM ORDER NO.724 OF 2012
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION

Kisham V
. Chintam
Vs

District Collector, Thane

CORAM
: S. C. DHARMADHIKARI, J. 

26th March 2013.

Pronounced on :
   Citation;2014(3) MHLJ629 Bom


This appeal from order is already admitted by this Court 
on 30th July 2012.  At that stage, following order was passed.

“Admit.  Hearing of the appeal is expedited and 
peremptorily fixed on 13th August 2012.  Mr.A.R.Patil 
waives   service   of   notice   of   final   hearing   on 
respondent Nos. 1 to 8.”
The   Civil   Application   No.927   of   2012   for   interim   reliefwas 
placed for orders before me and with the consent of the learned 
Advocates appearing for parties, the appeal itself is heard and 

disposed of at this stage.  Accordingly, I have heard the learned 
Counsel   Mr.Godbole   for   appellants   and   learned   Advocate 
General for respondents.
2]
This appeal from order challenges the order passed by the 
trial court below Exh.5 dated 3rd July 2012 in Special Civil Suit 
No.85 of 2012.  That special civil suit has been filed in the trial 
court by the plaintiffs against the State of Maharashtra and its 
officials.     That   is   alleging   that   the   appellants­   plaintiffs,   who 
shall be hereinafter referred to as plaintiffs, are owners of Gat 
No.16, Survey No.70A/1/1/B admeasuring 11.34 Rs situate at 
Kalambe   village   Taluka   Shahapur,   Dist.   Thane   and   more 

particularly described in para 1 of the plaint.  In para 2 of the 
plaint,   the   allegation   is   that   the   suit   property   i.e.   Gat   No.16 
bearing S.No.70A/1/1/B admeasuring 11.34 Rs was earlier part 
of S.No.70.  The area of S.No.70 was 48 acres 23 gunthas.  The 
said S.No.70 was further divided into 70A, 70B and 70C.   The 
said   sub­division   was   admeasuring   as   70A(48   acres   11 

gunthas), 70B (10 Gunthas ­Khan) and 70C (2 Gunthas­Khan). 
Survey   No.70A/1   was   part   of   S.No.70A   and   area   of   said 
S.No.70A/1   was   48   acres   and   2   gunthas.     Division   of 
S.No.70A/1   was   70A/1/1   and   70A/1/2.     S.No.70A/1/1   was 
further   divided   into   14   parts   i.e.   70A/1/1/1   to   70A/1/1/14. 
Out of this sub­division S.No.70A/1/1/13 was sub­divided into 
70A/1/1/13 and 70A/1/1B.  Survey No.70A/1 was divided into 
two separate Survey numbers viz., S.No.70A/1/1 (47 acres 33 
gunthas) and S.No.70A/1/2 (0 acres and 9 gunthas).   Survey 
No.70A/1/1 was further sub­divided into 14 hissas as follows:­

S.No.
Area
Acre
Guntha
============================
“70A/1/1/1
to
70A/1/1/7
20
20
70A/1/1/8 4 70A/1/1/9 4 70A/1/1/10 3 14
9 29
2 27
2 14
70A/1/1/13
70A/1/1/14
Total Area
9
70A/1/1/12

70A/1/1/11
26
14
47
33
Above mentioned areas are as per the Aakar Phod Patrak/ Kami 
Jast Patrak of S.No.70A/1/1.  It is pertinent to note that area of 
S.No.70A/1/1 Hissa 13 is 2 acre 14 gunthas i.e. 94 gunthas i.e. 
95.01 R.
It is further submitted that, the land bearing S.No.70A/1/1 
Hissa   No.13   situated   at   Village   Kalambe   was   owned   by 
Smt.Posanibai   Sayana   Chintam   and   Smt.Kuktabai   P   Chintam. 
In the year 1942 said land owners through Shri Pottana applied 
for   the   permission   for  non  agricultural   user  of  S.No.70A/1/1 
Hissa No.13.   By an order dated 31 st  March 1942 Mamlatdar, 
Shahapur was pleased to grant permission for non agricultural 
use in C.T.S.No.73A Hissa No.13 (S.No.70A/1/1 Hissa No.13) 
on the conditions specified in the said order viz., (I) residential 
building   should   be   constructed   in   the   land   admeasuring   444 
sq.yards 4 sq.ft. and latterine admeasuring 6 sq.yards 6 sq.ft as 
shown   in   the   sketch   prepared   by   Circle   Inspector   on   2 nd 
February 1942 and signed by the applicants – appellants.  Area 
admeasuring 904 sq.yds 4 sq.ft was directed to be kept open 
and on other conditions stated in the said order.  
3]
It   is   submitted   that   in   furtherance   of   N.A.   order, 
measurement was carried out.   As per that measurement, the 
non agricultural use was permitted and shown as 1365 sq.yds 
i.e. 11 gunthas and 3 Rs viz., 11.35 Rs.   The plaintiffs relied 
upon a map dated 30th December 1957.  The allegation is that 
in terms of this N.A. order and the measurement of 1957, “Kami 
Jast   Extract”   was   prepared   showing   the   details   of   area   of 
S.No.70A/1/1 Hissa No.13.   The land admeasuring 0 Acre 11 
gunthas and 3 aane i.e. 11.20 gunthas was separately shown as 
S.No.70A/1/1B,   a   copy   of   this   extract   is   also   produced   on 
record.     In   short   the   case   is   that   S.No.70A/1/1   was   further 

divided into two parts namely 70A/1/1/13 and S.No.70A/1/1B. 
That description was also given in the plaint at para 4.   The 
undisputed   position   emerging   from   the   record   is   that   the 
Dist.Judge,   Thane   on   5th  January   1988   sent   a   proposal   for 
acquisition of land from Village Kalambe Taluka Shahapur for 
construction  of  Court Building  and  residential  quarters.    This 
application/ proposal was forwarded by Additional Collector to 
Special   Land   Acquisition   Officer   with   a   direction   to   start 
acquisition proceedings under Land Acquisition Act, 1894.
3]
I   need   not   refer   to   in   extenso   to   the   notification   under 
section 6 and the details pertaining thereto inasmuch as it is 

stated in the plaint itself that an award was made in respect of 
the   land   bearing   S.No.70A/1/1   Hissa   No.13   and   the   area   of 
land under acquisition was declared as 83.77 Rs.   There is a 
reference made by both parties to the Award dated 8 th  March 
It   is   then   contended   that   the   District   Inspector   of   Land 
4]
1992, a copy of which is produced on record.
Records by his order dated 31 st  March 1990 implemented new 
scheme   for   the   land   situate   at   Village   Kalambe   and   in 
accordance with the said scheme, S.No.70A/1/1B was the land 
converted into N.A. user by order dated 31 st  March 1992 and 
was admeasuring 11 gunthas 3 Anna and 4 pai.  The plaintiffs 
states that on 12th March 2003 they addressed a letter to SLAO 
Thane stating that this land, which is now corresponding to Gat 
No.16 is admeasuring 11.34 Rs, is a separate non agricultural 
land and it is neither mentioned in the notification issued under 
section 4 or section 6 of the Land Acquisition Act nor in the 
Award dated 18th  April 1992.   It was further pointed out that 

the total area of   Gat No.70A/1/1/13 is 94 Rs and proposed 
acquisition is only to the extent of 83.77 Rs.   Therefore, N.A. 
land   has   not   been   taken   into   consideration   by   SLAO   while 
passing the award and it is, therefore, not the subject matter of 
In furtherance of the acquisition proceedings, new   map 
5]
the award.
came   to   be   prepared   but   that   was   incorrect.     The   Taluka 
Inspector of Land Records addressed a letter to SLAO on 15 th 
March 2003 informing him that the map of the land in question 
i.e. Gat No.16 appears to be incorrect.   It was further pointed 
out that a map bearing M.R.No.145 has not been given effect to 
in Kami Jast Extract of 1958.  The entire Hissa No.13 is shown 
on the map with reference to Gat No.16 and, therefore, the map 
be modified.
6]
Therefore, a new map bearing M.R.No.670 was prepared 
to show the land under acquisition admeasuring 83.77 Rs from 

Survey No.16.  A specific remark was inserted in  the map that 
proceedings for amalgamation and correction with reference to 
Gat No.16 are pending with Superintendent of Land Records, 
Maharashtra.
It   is   alleged   that   the   TILR   addressed   a   letter   to   the 
7]

plaintiffs on 22nd July 2004 informing that modification of map 
as provided by Section 31A is approved and new map will be 
prepared   within   15   days.     Thereafter,   the   new   map   is   relied 
upon.  It is stated that the TILR even addressed a letter to SLAO 
Thane informing him that the incorrect map has been corrected. 
It is then alleged that on 26 th December 2005, the SLAO Thane 
tried to obtain possession of the land S.No.70A/1/1 Hissa No.13 
but since the representative of the Civil Court, Shahapur was 
not present, the possession was not taken.   It is then alleged 
that on an application dated 2nd January 2006 of the plaintiff for 
measurement of Survey Nos. 10 and 91, it was carried out and 
map bearing M.R.932 came to be prepared.  It is stated that if 

the said map is perused incorrect portion can be traced and the 
encroachment is clearly done by defendant No.6, so as to save 
certain   adjoining   owners   and   their   encroachment.     It   is   then 
stated that on the application of Civil Court new map bearing 
No.1655 dated 2nd April 2008 came to be prepared to show the 
boundaries of the  land under  acquisition.    Thereafter on 11 th 

August 2008, TILR Shahapur issued a show cause notice to the 
land owners – plaintiffs seeking explanation as to why the map 
of   S.No.70A/1/1   Hissa   No.13   bearing   M.R.932   dated   2 nd 
January   2006   should   not   be   reviewed/   modified/   cancelled. 
This show cause notice was replied by the plaintiffs and they 
pointed out that such review proceedings are not maintainable. 
It is alleged that no order is passed in furtherance of the show 
cause notice and reply.  Then, it is stated that plaintiffs informed 
the   learned   Dist.Judge   Thane   regarding   encroachment 
committed   by   the   owners   of   S.No.70A/1/1   Hissa   No.8   (Gat 
No.13 Part).  It was pointed out that in view of the revised map 
issued, new measurement is required.   It is stated that on 25 th 

January 2011, the Deputy Director of Land Records, Shahapur 
issued   a   show   cause   notice   requesting   the   land   owners   to 
remain present at the time of measurement and measurement 
was   carried   out   in   February   2011   but   this   measurement   was 
objected to by the plaintiffs on 9 th  February 2011.   They also 
filed   an   appeal   under   section   247   of   the   Maharashtra   Land 
Revenue Code on 13th May 2011.  By letter dated 20 th May 2011 
the   District   Superintendent   of   Land   Records   informed   the 
plaintiffs that the said appeal is filed for fixing boundaries and 
hence not maintainable and disposed of.  Thus it is alleged that 
the   Authority   did   not   allow   the   plaintiffs   to   make   their 
submissions.     In   the   meanwhile,   the   Sub­Divisional   Officer, 
Bhivandi   addressed   a   letter   to   the   Superintendent   of   Land 
Records,   Thane   requesting   him   to   take   appropriate   steps   to 
cancel   the   mutation   Entry   No.1   by   which   Gat   No.16   was 
formed.  Reliance is placed upon a letter dated 31 st March 2011 
in that regard and it is alleged that without giving any notice to 
the land owners/ plaintiffs, the Deputy Superintendent of Land 

Records  passed   an   order   dated   2 nd  April   2011   cancelling   Gat 
No.16 and asked the plaintiffs to file objections for the proposed 
amendments   in   the   map.     Thereafter,   the   Deputy 
Superintendent of Land Records, passed an order on 6 th January 
2012 cancelling the map bearing No.670, 932 and 1655 dated 
14th August 2003, 1st July 2006 and 2nd April 2008 respectively. 
Being   aggrieved   and   dis­satisfied   by   this   order   the   plaintiffs 
filed   an   appeal   before   the   District   Superintendent   of   Land 
Records, Thane on 18th April 2012.
8]
It is, therefore, alleged that the suit property was never the 
subject   matter   of   acquisition.     There   was   no   question   of 
surrendering   possession   thereof   to   the   defendants.     The   suit 
property   was   not   acquired   by   the   defendants.     It   was 
surrounded by the compound of barbed wires having cement 
poles around and separate entrance gates with lock and key and 
the same was fully in possession of the plaintiffs since 1942 or 
thereabouts.     It   was   completely   removed   and   destroyed   high 

handedly with the help of local police in the presence of the 
members of the Shahapur Bar Association.  Thus, the objections 
and correspondence has not resulted in the possession of the 
plaintiffs   being   protected   and   making   such   allegations   and 
alleging that the cause of action for the suit arose on 1 st March 
2012, when the defendants forcibly dispossessed the plaintiffs 
ig
from the suit property that the suit was filed claiming following 
reliefs:­
“(a) that the suit may kindly be decreed with costs;
(b) that   this   Court   be   pleased   to   direct   the 
defendants   to   deliver   the   vacant,   peaceful   and 
physical possession of suit property to the plaintiffs;
© that   the   defendants   their   servant,   agent, 
representatives and/or any persons claiming through 
or   under   them   be   restrained   by   an   order   and 
permanent injunction of this Court from dealing with 
disposing of or alienating, encumbering, transferring, 
inducting any third party or parting with possession 
in respect of the suit property;
(d) that the defendants their servants, agents, 
representatives and/or any persons claiming through 
or   under   them   be   restrained   by   an   order   and 

9]
permanent injunction of this Court from putting up 
any construction and or developing the suit property 
and or granting any development right in favour of 
any third party, person or persons, in respect of the 
suit property;”
An   application   for   interim   reliefs   was   filed   in   this   suit 
claiming temporary injunction in furtherance of the aforequoted 
prayers.     The   defendants   were   served   with   the   papers   and 
proceedings and they filed their detailed affidavit in reply.
10] In the written statement/ reply of the original defendant 
Nos. 3 to 5 it has been alleged that the suit is false, frivolous, 
bogus and not bonafide.   It has been filed with a view to stall 
construction   of   civil   court   building.     The   plaintiffs   have 
suppressed material facts from the court.  The plaintiffs' whole 
case is based on existence of Gat No.16.  However, that itself is 
not existing.  What has been pointed out is that Gat No.16 was 
never in existence.   It was asserted that the property at Mauje 
Kalambe   Taluka   Shahapur   now   numbered   at   Gat   No.22   (old 

S.No.70/1/1/Hissa   No.13)   was   reserved   for   construction   of 
court building.   It has been acquired in 1992.   It admeasures 
83.77  Rs.     Out of  that  0­7­50   Rs is  a  road  from  Kalambe  to 
Borshi.     It   is   a   zilla   parishad   road.     That   portion   has   been 
excluded and, therefore, the remaining land  0­76­27 Rs stands 
in  the   name   of Dist.Court,   Thane  in  7/12  extracts.     The  suit 
property stated to be admeasuring 0­11­34 Rs which is also a 
part of larger property 83.77 Rs.  However, in the consolidation 
scheme, this area was wrongly assigned Gat No.16.  In fact the 
area of Gat No.16 has been shown twice and dis­advantage of 
that   is   being   taken   and   in   fact   that   Gat   No.16   has   been 
cancelled.  Once the Gat No.16 is treated as cancelled, then, the 
plaintiffs cannot claim to be owners of the said land.   In these 
circumstances, they are not entitled to get any interim reliefs. 
There is no prima facie case in their favour at all.
11] It was highlighted that old S.No.70A/1/1 Hissa No.13 was 
totally   admeasuring   0­93­77   Rs.   and   that   is   approximately   
acre and 14 gunthas.  Out of this land 0­10­0 Rs. was separated 
for Government mine.   That was assigned S.No.70A/1B.   The 
portion identified by the plaintiffs admeasuring 0­11­34 is part 
of S.No.70A/1/1B and that is excluded and after exclusion of 
the   Government   land   the   S.No.70A/1/1/   Hissa   No.13 
admeasured 0­83­77 Rs.   In these circumstances all averments 
in   para   4   of   the   plaint   are   false.     In   the   rest   of   the   written 
statement, this aspect has been highlighted and all allegations 
to the contrary have been denied.  There is an explanation given 
with regard to the notices and orders made from time to time.
12] Upon this material the learned Trial Judge heard parties. 
He perused the documents and held that there is no prima facie 
case nor is the balance of convenience in favour of plaintiffs and 
they   suffer   no   irreparable   loss   and   injury.     Rather   granting 
interim   reliefs   would   cause   hindrance   and   obstacle   to   the 
ongoing construction activity at site viz., construction of court 
building.  In these circumstances, by the impugned order dated 

3rd July 2012, the interim injunction was denied and application 
Exh.5 was dismissed.
13] It is this order which is challenged in this appeal.
14] Mr.Godbole,   learned   Counsel   appearing   for   appellants 
ig
submits that the impugned order is ex facie erroneous, illegal 
and perverse.  He submits that the learned Judge has accepted 
version   of     the   respondents   –   original   defendants   as   if   it   is 
conclusive at this stage.   Now such a conclusive opinion being 
rendered at an interlocutory stage would mean that the learned 
Judge has exceeded his powers.  Just as there was version of the 
respondents equally, there is an arguable case of the plaintiffs. 
That is based on the fact that non agricultural order of 1942 has 
not been cancelled.   The Kami Jast Patrak of 1957 is also not 
cancelled.  Therefore, a prima facie case is made out inasmuch 
as   the   portion   of   11.34   Rs   cannot   be   said   to   be   part   of   the 
acquired land.  There is a prima facie case because this portion 
has been carved out as separate area.   The learned Judge has 
failed to advert to the materials with regard to separate area. 
Mr.Godbole   has   relied   upon   the   1942   non   agricultural   order, 
Kami   Jast   Patrak,   the   maps   and   the   measurement   records 
prepared from time to time to urge that once the action of the 
respondents was highhanded and arbitrary, then, the trial court 
should have been careful enough in scrutinising the record.  He 
should not have permitted the defendants to proceed and make 
construction   once   there   is   an   arguable   case   made   out.     The 
plaintiffs may or may not succeed at the trial but once there are 
serious  issues arising and   they require   trial  and  adjudication, 
then,   the   learned   Judge   should   have   not   refused   interim 
injunction.
15] Mr.Godbole   complains   that   there   is   absolutely   no 
discussion on the map in the judgement and order.  Inviting my 
attention   to   page   38/39   of   the   appeal   paperbook,   which 
contains paras 18 and 19 of the impugned order, Mr.Godbole 
submits   that   the   learned   Judge   has   merely   noted   rival 
contentions but has failed to take into account the consequences 
of N.A.orders, Kami Jast Patrak, maps which show that despite 
the acquisition, there is a substantial portion of the land which 
is a private property and which cannot be touched except by 
due process of law.   An attempt is made by the respondents – 
original   defendants   to   demonstrate   that   the   said   land   is   also 
part of the acquired land.  Such an attempt and the highhanded 
act of the respondents led to the institution of the suit.  For all 
these reasons, merely because the construction activity of court 
building is going on, is no ground to refuse interim injunction.
16] Mr.Khambata,   Learned   Advocate   General   appearing   on 
behalf of the respondents on the other hand has submitted that 
the  appellants  are  not  entitled  to  interim  reliefs.    An interim 
order is discretionary and equitable relief.  The appellants have 
not approached the Court with clean hands.  The appellants are 
guilty of suppressing material facts.   The appellants never had 

any right in the property.   The appellants' land stood acquired 
and   stood   vested   in  the   State.     Once   the   appellants   have   no 
right, title and interest of any nature in the immovable property, 
then,   the   present   suit   was   not   maintainable.     If   it   was   not 
maintainable,   then,   interim   injunction   could   not   have   been 
granted.  The trial court is right in denying the same as there is 
no prima facie case, balance of convenience is not in favour of 
the   appellants   and   the   appellants   will   not   suffer   any   loss   or 
injury.     Instead   public   interest   would   suffer   adversely   if   the 
court building does not come up and in these circumstances, the 
interim injunction should not be granted.  The learned Advocate 
General in  the alternative and on merits has argued that the 
trial   Judge   has   given   weightage   to   primary   documents   and 
records in relation to the land.  These primary records indicate 
that there is absolutely no foundation for the suit claim.   The 
Gat No.16 does not exist.   The order passed on 24 th  February 
2012 cancells all earlier entries.  Mr.Khambata has pointed out 
that the very compilation which has been relied upon by the 
appellants   and   containing   documents   will   show   that   the 
appellants have collected compensation for the portion of 11.34 
Rs.  Even if that is assuming to be a non agricultural land,  that 
is part and parcel of the acquired land.  If it is part and parcel of 
the same and has been taken over by the State in accordance 
with law after paying compensation, then, there is absolutely no 
prima facie case.
17] Mr.Khambata   has   relied   upon   the   documents   and 
submitted that the order passed in 1942 styled as N.A.order is 
of no assistance to the appellants.  If there is no separate survey 
number given to the suit land, even in 1971 and assuming that 
this 1942 N.A. order was in force, then, the appellants cannot 
claim   any   interim   injunction.     Mr.Khambata   has   taken   me 
through   all   the   documents,   including   7/12   extracts   and   has 
urged   that   even   after   the   N.A.   order   of   1942,   there   is   no 
creation of separate plot.   The N.A.Order itself cannot amount 
to  creation of a separate or new plot.  He submits that the Kami 

Jast Patrak is not a primary document.  It was never acted upon. 
In these circumstances, if the primary record does not indicate 
that there was any separate plot, which stood out of acquisition 
proceedings and which continued to belong to the appellants, 
then, their claim itself falls to the ground and is untenable.  The 
interim injunction.
trial judge, therefore, has rightly dismissed the application for 
18] With   the   assistance   of both  the  learned   Counsel,   I  have 
perused   the   appeal   paper   book   and   the   compilation   of 
documents   tendered   by   Mr.Godbole.     Mr.Godbole   has   placed 
reliance  upon the  7/12 extracts  and  has  stated  that  it shows 
that   the   land   belongs   to   the   appellants   and   has   been 
demarcated   as   Gat   No.16   (NA),   admeasuring   11.34   Rs. 
Mr.Godbole, then, has relied upon a Kami Jast Patrak and has 
submitted that insofar as Hissa No.13 is concerned, there is an 
endorsement in the remark column that a portion admeasuring 
11.34 Rs is a N.A. plot and has been assigned another survey 

number i.e. 70A/1/1B.  Mr.Godbole then relied upon a map at 
page 91 of the paper book and submits that even that shows 
that there is Gat No.16 as well and this is a revised/ corrected 
map.     Mr.Godbole   has   also   relied   upon   the   minutes   of   the 
meeting dated 26th  December 2005 to urge that Gat No.16 is 
not included in the acquired portion and, therefore, is not a part 
of the acquired land.  Mr.Godbole also relies upon a letter dated 
11th  August   2008   addressed   by   the   Taluka   Inspector   of   Land 
Records, to the plaintiffs and the Panchanama dated 1 st  March 
2012.  
19] Thus, relying upon all this it is the case of the appellants 
that there was a separate portion and which was not part of the 
acquired land and which fact was known to the respondents, 
yet, they proceeded to take it over highhandedly and without 
due process of law.
20] In   that   regard,   what   has   been   clarified   by   the   State 

Government is that it is false to suggest that any such attempt 
has  been  made   or  any  high   handed   act has  been  performed. 
The documents on record reflect the correct position at site.  It 
has been pointed out that a notification under section 4 of the 
Land Acquisition Act was issued on 24 th April 1989 in respect of 
plot of land S.No.70A/1/1/Hissa 13 admeasuring 83.77 Rs from 
village   Kalambe   Taluka   Shahapur,   the   acquisition   was   for 
construction   of   Court   building   and   residential   quarters   of 
judicial officers.  The declaration under section 6 of the L.A.Act 
was issued on 19th April 1990.  The suit plot admeasuring 11.34 
Rs is part and parcel of the acquired land admeasuring 83.77 
Rs.  The 7/12 extract of the acquired land are relied upon and 
equally the Award dated 18th April 1992.
21] Mr.Godbole produces for my perusal the award in this case 
and what that clarifies is that the acquired land includes the suit 
property.  On 18th April 1992, the award, a copy of which is at 
page   72   of  the   compilation,   in  the   column  “land   notified   for 

acquisition” and “area”, states as under:­
“(C) Lands notified for Acquisition:­
The lands finally notified for acquisition in the 
Section 6 notification is as under:­
Taluka
S.No.H.No.
Village
(2)
Area:­
0.83.77

Kalambe Shahapur   70A/1/1­13
Approx.area
H.
Rs.
The   lands   proposed   for   acquisition   has   been 
jointly   measured   by   the   surveyors   of   the   additional 
D.I.L.R.,   Thane   and   the   representative   of   the 
acquiring   body.     Joint   measurement   plans   and 
statements   were   kept   upon   for   inspection   of   the 
interested persons.     No disputes about the areas of 
the   lands   showing   joint   measurement   plans   and 
statements   was   raised   by   any   of   the   interested 
persons.  I, therefore, accept and confirm the area of 
the land under acquisition for the purposes of Award 
as shown below:­
“It   was   found   that   a   pacca   road   is   passing 
through   this   land   under   acquisition.     This   road   is 
already shown in the joint measurement plans.   The 
area under this road is 0.7.50 acres under the road. 
So excluding area of 0.7.50 area from total area of 

0.83.77 Acres, the area under acquisition, and liable 
for compensation is 0.76.27 Acres.”
22] To my mind, when this was the material produced, then, 
the  trial Court rightly called  upon the appellants plaintiffs  to 
demonstrate as to how they still claim that the suit property is 
not part of the acquired land.   In that regard, what has been 

relied upon is the consolidation scheme.  The clarification given 
is   that   in   the   year   1990,   which   is   prior   to   the   Award,   a 
consolidation   scheme   was   implemented   for   the   entire   village 
Kalambe   under   the   provisions   of   Bombay   Prevention   of 
Fragmentation   and   Consolidation   of   Holdings   Act,   1947.     At 
that   time,   various   survey   numbers   were   converted   into   Gat 
numbers   and   consolidated   village   maps   were   prepared   and 
corresponding numbers were given in a separate booklet for the 
village.  The acquired land under the said scheme were forming 
Gat   No.22.     However,   due   to   inadvertence,   the   suit   plot 
admeasuring 11.34 Rs was shown as separate piece of land on 
the village map prepared by the concerned Department.   The 

7/12 extract for separate gat number was also prepared by the 
then consolidation officer erroneously.   Then reliance is placed 
also  on certain  correspondence   and   maps but  what has  been 
through out the stand of the State is that once there was an 
acquisition and vesting as the possession was also taken over on 
31st  January 2006, whereas the suit is filed in the year 2012, 

then, merely by relying upon some isolated act, the appellants – 
plaintiffs   cannot   file   the   instant   suit   and   claim   interim 
injunction.   They have yet to prove their case.   The burden is 
squarely on them.  At the prima facie stage, they are unable to 
dislodge   the   contents   of   the   Award   and   other   overwhelming 
documentary evidence.
23] The State has also clarified that when the plaintiffs were 
taking undue advantage of an error committed by Government 
officers,   that   in   January   2012   the   District   Superintendent   of 
Land Records, Thane initiated proceedings under section 32(1) 
of   the   Consolidation   Act   (Act   of   1947)   to   rectify   the   error 

regarding S.No.16 and also to correct corresponding mutation 
entry   and   revenue   record.     He   issued   public   notice   on   12 th 
January 2012.     An opportunity was given to the appellants – 
plaintiffs to file their objections, they were given hearing and 
ultimately he passed an order on 24 th  February 2012 to rectify 
the   error.     That   there   stood   any   existing   land   and   outside 
acquisition   as   a   separate   piece   of   N.A.   land   to   the   extent   of 
11.34 Rs (Gat No.16) was appellants' claim and which has been 
specifically   rejected.     All   earlier   maps   prepared   by   the 
department are cancelled.  Even the 7/12 extracts and mutation 
entries were cancelled and correspondingly the mutation entry 
No.547 dated 27th  February 2012 was inserted in the revenue 
records.   In these circumstances and when all the procedures 
were   completed,   tenders   were   floated   and   allocation   of 
Rs.30.30 Crores for the project of construction of court building 
has been made, the construction is going on, that this is not a fit 
case where a public project can be halted or its implementation 
thwarted  in  the  manner suggested  by the  appellants.    To my 

mind, each of this material was relevant and germane and the 
trial court did not commit any error in taking that into account. 
The   trial   court   has   applied   the   correct   principles   and   has 
observed that prima facie the only dispute is as to whether the 
suit property forms a part of the acquired land.  In that regard, 
the   Survey   Nos.70A/1/1   Hissa   No.13   (Gat   No.22)   is   the 
ig
acquired   land   and   what   is   the   extent   and   how   much   it 
admeasures has been, then, considered and with reference to 
specific records.  Each of the documents that Mr.Godbole relies 
upon have been considered in paras 21 and 22 of the impugned 
order.     It   is   not   as   if   the   trial   court   ignored   any   material   or 
brushed   aside   any   relevant   document.     Each   and   every 
document produced including the Akar Fod Patrak was taken 
into consideration.  However,  even after the land admeasuring 
11.34   Rs   was   shown   as   non   agricultural,   there   is   no   7/12 
extract in relation to the same.  Mr.Godbole states that this is an 
incorrect   finding   because   there   is   a   7/12   extract   and   which 
clearly shows the land as N.A.  He relies upon the 7/12 extract 

of 1990 in this behalf.  He also relies upon the Kami Jast Patrak. 
However, once there is an order passed on 24 th January 2012, it 
may   have   been   challenged   but   it   is   yet   not   disturbed   or 
interfered with, leave alone set aside, then, the trial court did 
not commit any error in holding that any such documents or 
maps  cannot  be   now   taken   into  consideration,   once   they  are 

cancelled.  The trial court has rightly observed that if there is no 
document   which   show   that   the   suit   property   has   been 
earmarked as separate land for N.A.use, then, the acquisition 
record cannot be brushed aside.  The award is made by the very 
same revenue officer in his capacity as Special Land Acquisition 
Officer.   He  had before him all the maps, measurements and 
records   and   it   is   only   then,   he   considered   the   claim   of   the 
appellants   for   compensation.     In   these   circumstances,   to 
displace and  dislodge the statements made in the award and 
which is of 18th  April 1992 at this prima facie state would be 
improper.  The learned Judge has referred to each of the maps 
and it is erroneous on the part of the appellants to urge that 

they have been brushed aside.  The learned Judge has referred 
to them and equally to the further steps taken culminating in 
the order dated 24th  February 2012.   It is after considering all 
these   materials,   that   he   arrived   at   a   conclusion   that   the 
appellants   –   plaintiffs   have   failed   to   make   out   a   prima   facie 
case.  The Balance of convenience is also not in their favour and 

they will not suffer grave or irreparable loss, harm and injury 
but construction of the court building is a public project and if it 
is stopped at this stage, that would be not in public interest. 
The overwhelming public interest  is paramount in such cases 
whereas   if   the   appellants   ultimately   succeed,   they   can   be 
compensated in terms of money or with appropriate direction.
24] To my mind, such a conclusion does not suffer from any 
error  of  law  or  perversity,   leave   alone,   serious  legal  infirmity 
warranting   interference   in   my   appellate   jurisdiction.   By   no 
stretch   of   imagination,   the   observations   and   findings   at   this 
prima   facie   stage   can   be   said   to   be   perverse.     In   such 

circumstances, I have no alternative but to dismiss this appeal. 
The   appeal   is   accordingly   dismissed.     No   costs.     Civil 
application, if any, to stand dismissed in view of dismissal of the 
appeal.

(S. C. DHARMADHIKARI, J)



Print Page

No comments:

Post a Comment